BLD-Final | 12/5/2019 | 12/6/2019 | 12/6/2019 | A | PASS |
Tell Riley
|
|
|
Mike Phone #: ###-####
|
DOC - Permit Finaled | 12/6/2019 | 12/6/2019 | 12/6/2019 | P | PASS |
Tell Riley
|
|
|
|
BLD-Framing/Rough-in | 6/24/2019 | 6/24/2019 | 6/24/2019 | P | PASS |
Tell Riley
|
|
|
Mike Phone #: ###-####//HVAC, electrical, and plumbing rough ins complete.//ok to cover framing.//garage insulation ok//
|
BLD-Framing/Rough-in | 6/19/2019 | 6/19/2019 | 6/19/2019 | P | NR |
Tell Riley
|
|
|
Mike Phone #: ###-####//obtain HVAC permit and inspection. //Call for Re-inspection//
|
BLD-Energy code compliance | 6/11/2019 | 6/11/2019 | 6/11/2019 | P | PART |
Tell Riley
|
|
|
Mike, Energy code and insulation. Phone #: ###-####//energy inspection ok per plans//master bedroom addition only//
|
BLD-Wall Bracing | 6/10/2019 | 6/10/2019 | 6/10/2019 | P | PASS |
Tell Riley
|
|
|
shear roof // Mike Phone #: ###-####// shear for garage addition//ok per plans.
|
BLD-Framing/Rough-in | 6/7/2019 | 6/10/2019 | 6/10/2019 | A | PART |
Tell Riley
|
|
|
Mike Phone #: ###-####,, master add only/ ok to insulate. will call for garage when ready.
|
BLD-Wall Bracing | 5/28/2019 | 5/28/2019 | 5/28/2019 | A | PART |
Brandon Shaw
|
|
|
Addition only, garage to be at a later date...
|
BLD-Footing | 5/14/2019 | 5/15/2019 | 5/15/2019 | A | PASS |
Brandon Shaw
|
|
|
Graig Phone #: ###-####
|
BLD-Footing | 5/13/2019 | 5/13/2019 | 5/13/2019 | P | PART |
Jim Sly
|
|
|
Greg Phone #: ###-#### Garage only.....OK.
|
BLD-Foundation | 4/22/2019 | 4/22/2019 | 4/22/2019 | P | PASS |
Jim Sly
|
|
|
Greg Phone #: ###-####
|
BLD-Footing | 4/17/2019 | 4/18/2019 | 4/18/2019 | A | PASS |
Jim Sly
|
|
|
JON- Please go in the late morn, thank you
|