Information based on query as of Monday, May 13, 2024.
Permit Information
Permit NumberBLD19-01208
StatusFinaled
Name HHS CONSTRUCTION LLC
Site Address 6038 E BARBER DR
Project NameHarris North Lot 97 Block 1
Customer Number 
ePlanReviewYes
Description
***W.U.I. Foothills: Class "A" Roof and Non-Combustible Construction Required*** Permit for the construction of a new 3159 sq. ft., one story single family dwelling with 3 bedrooms, 2.5 bathrooms, approximately 290 sq. ft. of covered patio/porch and a 828 sq. ft. attached garage per the approved plans and any notations. Prescriptive Energy Compliance. SP-01 zoning and setbacks per planning. ***RDP***
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/29/201910/30/201910/30/2019APASS
DetailsBrandon Shaw
les Phone #: ###-####
DOC - Permit Finaled10/30/201910/30/201910/30/2019PPASS
DetailsBrandon Shaw
BLD-Blower Door Test Results10/30/201910/30/201910/30/2019ADONE
DetailsBrandon Shaw
ACH50- 1.71
BLD-Energy code compliance7/31/20198/1/20198/1/2019APASS
DetailsBrandon Shaw
les Phone #: ###-####
BLD-Framing/Rough-in7/29/20197/30/20197/30/2019APASS
DetailsBrandon Shaw
Les Phone #: ###-####
BLD-Ceiling Grid Inspection7/23/20197/24/20197/24/2019APASS
DetailsJim Storey
soffett // Les Phone #: ###-####
BLD-Wall Bracing6/25/20196/25/20196/25/2019AFAIL
DetailsBrandon Shaw
All exterior sheathing to be nailed to sill plates with approved fasteners...
Renail all edge and field nailing...
BLD-Wall Bracing6/24/20196/25/20196/25/2019APASS
DetailsBrandon Shaw
Corrections SAT...
BLD-Wall Bracing6/21/20196/21/20196/21/2019PFAIL
DetailsJim Storey
Wes Phone #: ###-#### house wraped w/o insp.
BLD-Wall Bracing6/11/20196/11/20196/11/2019PCANC
DetailsBrandon Shaw
Wrong permit #...
BLD-Foundation6/4/20196/4/20196/4/2019PPASS
DetailsJim Storey
Dion-foundation wall Phone #: ###-####
BLD-Footing6/3/20196/3/20196/3/2019PPASS
DetailsJim Storey
Dion Phone #: ###-####