Permit Information
Permit NumberBLD19-01282
StatusFinaled
Name KINCAID CONSTRUCTION LLC
Site Address 1840 N MOCKBEE PL
Project NameMockbee House - 1840 N. Mockbe
Customer Number 
ePlanReviewYes
Description
**PLAN MODIFICATION - changes to site drainage per hillside requirements JJN 11/4/19** **HILLSIDE** **WUI FOOTHILLS ZONE A** **PRESCRIPTIVE ENERGY REQUIREMENTS** Permit for the construction of a new 3588 sq. ft., two story (first story 1856 sq. ft., second story 1300 sq. ft., basement 432 sq. ft.) single family dwelling with 3 bedrooms, 3.5 bathrooms, approximately and a 590 sq. ft. attached garage per the approved plans and any notations. R-1B zoning and setbacks per planning. JJN SPRINKLERS ARE REQUIRED AND BEING PROVIDED, AS NOTED ON THE COVER SHEET / SITE PLAN. LGMA letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.

An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call 208-608-7070 to schedule an inspection.



All disturbed slopes included in the construction of this project must be stabilized and approved by Public Works before a Final Occupancy Permit is granted. If weather conditions prohibit revegetation and stabilization activities, the contractor shall provide a bond/surety agreement or an irrevocable letter of credit in the amount of 110% of the cost estimated by the project engineer to enable stabilization of the site. Call 208-608-7168 for an inspection.

Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/20/20204/20/20204/20/2020PPASS
DetailsBrandon Shaw
HVAC is now completed and signed off Phone #: ###-#### Inspection requested via web by Larry Kincaid
DOC - Permit Finaled4/20/20204/20/20204/20/2020PPASS
DetailsBrandon Shaw
BLD-Final4/1/20204/2/20204/2/2020PPART
DetailsBrandon Shaw
Temp C of O ia approved for 30 days ending 4Mar20...
Needs MEC19-04186 final, no other issues...
BLD-Final4/1/20204/2/20204/2/2020ACANC
DetailsBrandon Shaw
I did a pre-conference walk through with Tell Riley for this project and we are now ready for the final. He might be best to do the final since we already went through all the items. Please call prior to coming to the site so I can make sure and be their. Thanks, Phone #: ###-#### Inspection requested via web by Larry Kincaid
BLD-Conference3/24/20203/24/20203/24/2020PDONE
DetailsTell Riley
I would like to schedule a conference or job site meeting to discuss all items we will need to get the project final inspection Phone #: ###-#### Inspection requested via web by Larry Kincaid
BLD-Foundation1/13/20201/13/20201/13/2020PPASS
DetailsBrandon Shaw
Work in progress...
Frost protection is reqired...
BLD-Footing1/8/20201/9/20201/9/2020APASS
DetailsBrandon Shaw
Need rebar inspection for retaining wall footers
Thanks, Inspection requested via web by Larry Kincaid
BLD-Foundation12/23/201912/26/201912/26/2019PPASS
DetailsBrandon Shaw
Work in progress...
BLD-Footing12/18/201912/19/201912/19/2019APASS
DetailsBrandon Shaw
need footing rebar inspection at retaining wall Inspection requested via web by Larry Kincaid
BLD-Energy code compliance11/22/201911/22/201911/22/2019PPASS
DetailsBrandon Shaw
OK to cover...
BLD-Wall cover11/22/201911/22/201911/22/2019PCANC
DetailsBrandon Shaw
Inspection requested via web by Larry Kincaid
BLD-Framing/Rough-in11/18/201911/19/201911/19/2019APASS
DetailsBrandon Shaw
Inspection requested via web by Larry Kincaid
BLD-Energy code compliance11/18/201911/19/201911/19/2019APART
DetailsBrandon Shaw
Air/foam seal...
BLD-Foundation11/18/201911/18/201911/18/2019PPART
DetailsBrandon Shaw
Work in progress...
BLD-Framing/Rough-in11/18/201911/18/201911/18/2019PCANC
DetailsBrandon Shaw
>> Inspection requested via web by Larry Kincaid Inspection cancelled from web by: Larry Kincaid
BLD-Footing11/12/201911/13/201911/13/2019APASS
DetailsBrandon Shaw
rebar inspection for retaining wall footer

Thanks, Inspection requested via web by Larry Kincaid
BLD-Concrete10/24/201910/24/201910/24/2019PPASS
DetailsBrandon Shaw
Work in progress...
West wall...
BLD-Framing/Rough-in10/7/201910/8/201910/8/2019APART
DetailsBrandon Shaw
Need to schedule an inspection for the roof underside so we can do a spray foam insulation before we install fire sprinkler lines.
BLD-Footing9/26/20199/27/20199/27/2019APASS
DetailsBrandon Shaw
Work in progress...
BLD-Wall Bracing9/20/20199/23/20199/23/2019APART
DetailsBrandon Shaw
Exterior only...
Interior shear and hold downs to be completed before framing rough-in...
BLD-Foundation7/23/20197/24/20197/24/2019APASS
DetailsDave Hannah
Inspection requested via web by Larry Kincaid
BLD-Footing7/17/20197/18/20197/18/2019APASS
DetailsBrandon Shaw
need rebar inspection for footings. Concrete pump and concrete delivery is scheduled for 11:00am. Thursday thanks
Phone #: ###-#### Inspection requested via web by Larry Kincaid
BLD-Foundation6/26/20196/26/20196/26/2019PPART
DetailsTony Young
rebar inspection for basement walls Phone #: ###-#### Inspection requested via web by Larry Kincaid// work in progress on the basement walls,, ok
BLD-Footing6/14/20196/14/20196/14/2019PPART
DetailsTony Young
Jerry Phone #: ###-####,, basement footing ok
BLD-Footing6/13/20196/14/20196/14/2019APART
DetailsTony Young
Jerry Phone #: ###-####,, basement footing