BLD-Final | 3/12/2020 | 3/13/2020 | 3/13/2020 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Kristy Newkirk
|
DOC - Permit Finaled | 3/13/2020 | 3/13/2020 | 3/13/2020 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Conference | 3/12/2020 | 3/13/2020 | 3/12/2020 | A | CANC |
Tony Young
|
|
|
We are waiting on a plumbing final so this may become the real final is we pass that. Phone #: ###-#### >> Inspection requested via web by Kristy Newkirk Inspection cancelled from web by: Kristy Newkirk
|
BLD-Energy code compliance | 1/3/2020 | 1/7/2020 | 1/8/2020 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Kristy Newkirk
|
BLD-Wall cover | 1/3/2020 | 1/7/2020 | 1/7/2020 | A | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Kristy Newkirk//ok to cover when fire blocks are foamed at electrical and plumbing penetrations//
|
BLD-Energy code compliance | 12/31/2019 | 1/3/2020 | 1/3/2020 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Kristy Newkirk// insulation ok,,just needs fire blocks
|
BLD-Framing/Rough-in | 12/31/2019 | 1/3/2020 | 1/3/2020 | A | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Kristy Newkirk// needs fire blocks at the ceiling lines,, ok to insulate
|
BLD-Framing/Rough-in | 12/30/2019 | 1/2/2020 | 12/31/2019 | A | CANC |
Tony Young
|
|
|
Phone #: ###-#### >> Inspection requested via web by Kristy Newkirk Inspection cancelled from web by: Kristy Newkirk
|
BLD-Energy code compliance | 12/27/2019 | 12/31/2019 | 12/30/2019 | A | CANC |
Tony Young
|
|
|
Phone #: ###-#### >> Inspection requested via web by Kristy Newkirk Inspection cancelled from web by: Kristy Newkirk
|
BLD-Framing/Rough-in | 12/27/2019 | 12/31/2019 | 12/30/2019 | A | CANC |
Tony Young
|
|
|
I''m not sure if this is the correct inspection. We need an ok to cover so we can get drywall installed. Let me know if I need to schedule something different. Thanks, Kristy ###-#### Phone #: ###-#### >> Inspection requested via web by Kristy Newkirk Inspection cancelled from web by: Kristy Newkirk
|
BLD-Conference | 12/11/2019 | 12/13/2019 | 12/13/2019 | A | PART |
Tony Young
|
|
|
Framing conference (no final HVAC inspection yet). Can you call Hans Glenn to meet on site for the conference ###-#### Phone #: ###-#### Inspection requested via web by Kristy Newkirk,, walk through only,, needs trades,, will need fire blocking
|
BLD-Wall Bracing | 11/21/2019 | 11/22/2019 | 11/22/2019 | P | PASS |
Tony Young
|
|
|
Shear inspection Phone #: ###-#### Inspection requested via web by Kristy Newkirk
|
BLD-Wall Bracing | 11/20/2019 | 11/21/2019 | 11/21/2019 | A | NR |
Tony Young
|
|
|
Shear inspection Phone #: ###-#### Inspection requested via web by Kristy Newkirk,, conf. only
|
BLD-Foundation | 9/4/2019 | 9/5/2019 | 9/5/2019 | P | DONE |
Tony Young
|
|
|
BRUCE Phone #: ###-####,, poured
|
BLD-Footing | 9/3/2019 | 9/4/2019 | 9/4/2019 | A | PART |
Tony Young
|
|
|
BRUCE Phone #: ###-####,, work in progress,, ok to pour when ready
|