BLD-Final | 2/10/2020 | 2/10/2020 | 2/10/2020 | P | PASS |
Dave Hannah
|
|
|
Call Dan For access Phone #: ###-#### Inspection requested via web by Daniel Appel
|
DOC - Permit Finaled | 2/10/2020 | 2/10/2020 | 2/10/2020 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 2/5/2020 | 2/6/2020 | 2/6/2020 | P | FAIL |
Brandon Shaw
|
|
|
Need ELE and Mech finals...
|
BLD-Energy code compliance | 12/2/2019 | 12/3/2019 | 12/3/2019 | A | PASS |
Brandon Shaw
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Wall cover | 12/2/2019 | 12/3/2019 | 12/3/2019 | A | CANC |
Brandon Shaw
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Framing/Rough-in | 12/2/2019 | 12/3/2019 | 12/3/2019 | A | PASS |
Brandon Shaw
|
|
|
Corrections SAT...
|
BLD-Framing/Rough-in | 11/25/2019 | 11/26/2019 | 11/26/2019 | A | FAIL |
Brandon Shaw
|
|
|
Per plans- (2) 2x10 header at front bedroom not installed... Per shear pg- Interior shear walls to be as per plans... Headers (2) at bottom of stairs, to be positively fastened with hangers... OK to insulate...
|
BLD-Wall Bracing | 11/8/2019 | 11/12/2019 | 11/12/2019 | A | PASS |
Brandon Shaw
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Foundation | 10/25/2019 | 10/28/2019 | 10/28/2019 | A | PART |
Jim Storey
|
|
|
wall // Chris Phone #: ###-#### pwoi set backs ok
|
BLD-Foundation | 10/25/2019 | 10/25/2019 | 10/25/2019 | P | DEFR |
Jim Storey
|
|
|
wall // Chris Phone #: ###-####//out of time
|
BLD-Footing | 10/17/2019 | 10/17/2019 | 10/17/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 10/16/2019 | 10/17/2019 | 10/17/2019 | A | NR |
Brandon Shaw
|
|
|
CHRIS Phone #: ###-####
|
BLD-Footing | 10/15/2019 | 10/16/2019 | 10/16/2019 | A | NR |
Brandon Shaw
|
|
|
Chris Phone #: ###-####
|