BLD-Final | 12/26/2019 | 12/26/2019 | 12/26/2019 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
DOC - Permit Finaled | 12/26/2019 | 12/26/2019 | 12/26/2019 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Blower Door Test Results | 12/26/2019 | 12/26/2019 | 12/26/2019 | P | PASS |
Dave Hannah
|
|
|
4.2
|
BLD-Final | 12/17/2019 | 12/17/2019 | 12/17/2019 | P | NR |
Mike Jordan
|
|
|
garage door code is 2468, fire door will be open. Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Energy code compliance | 10/31/2019 | 10/31/2019 | 10/31/2019 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Framing/Rough-in | 10/31/2019 | 10/31/2019 | 10/31/2019 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Framing/Rough-in | 10/29/2019 | 10/30/2019 | 10/30/2019 | A | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Provide strong back on gable end in garage. Strap double top plate break in garage. Provide more nails in king studs to headers.(ALL). Provide purlins on top chords of B2, B3 and B4 trusses at over build. Ok to insulate. Correction notice posted.
|
BLD-Framing/Rough-in | 10/24/2019 | 10/25/2019 | 10/25/2019 | A | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Still need mech rough in inspection prior to framing inspection.
|
BLD-Wall Bracing | 10/15/2019 | 10/16/2019 | 10/16/2019 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Wall Bracing | 10/14/2019 | 10/15/2019 | 10/15/2019 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Foundation | 9/30/2019 | 10/1/2019 | 10/1/2019 | P | PASS |
Mike Jordan
|
|
|
dANE- FOUNDATION WALL Phone #: ###-####
|
BLD-Footing | 9/27/2019 | 9/30/2019 | 9/30/2019 | P | PASS |
Mike Jordan
|
|
|
Jerry Phone #: ###-####
|