Permit Information
Permit NumberBLD19-02573
StatusFinaled
Name HHS CONSTRUCTION LLC
Site Address 5997 E FOXGROVE DR
Project NameHarris North Lot 15 Block 2
Customer Number 
ePlanReviewYes
Description
**HILLSIDE** **W.U.I. HILLSIDE ZONE A CLASS "A" ROOF AND NON-COMBUSTIBLE EXTERIOR SIDING REQUIRED** **PRESCRIPTIVE ENERGY REQUIREMENTS** Permit for the construction of a new 3961 sq. ft., two story (first story 2608 sq. ft., second story 1353 sq. ft.) single family dwelling with 5 bedrooms, 4.5 bathrooms, approximately 422 sq. ft. of covered patio/porch and a 1074 sq. ft. attached garage per the approved plans and any notations. SP-01 zoning and setbacks per planning. JJN ***SPRINKLERS ARE REQUIRED***LGM A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.

Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/12/20205/13/20205/13/2020APASS
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by Kyle Seick
DOC - Permit Finaled5/13/20205/13/20205/13/2020PPASS
DetailsBrandon Shaw
BLD-Blower Door Test Results5/13/20205/13/20205/13/2020ADONE
DetailsBrandon Shaw
ACH50- 3.96
BLD-Final5/4/20205/5/20205/5/2020ANR
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by Kyle Seick
BLD-Energy code compliance2/3/20202/3/20202/3/2020PPASS
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by Kyle Seick
BLD-Framing/Rough-in1/28/20201/28/20201/28/2020PPART
DetailsBob Archibald
Phone #: ###-#### Inspection requested via web by Kyle Seick. Ok for insulation, all trades appoved roughins.
BLD-Framing/Rough-in1/24/20201/27/20201/27/2020AFAIL
DetailsBrandon Shaw
No city approved plans on site...
BLD-Other11/20/201911/21/201911/21/2019APASS
DetailsBrandon Shaw
Soffitt Phone #: ###-#### Inspection requested via web by Kyle Seick
BLD-Wall Bracing10/17/201910/17/201910/17/2019PPART
DetailsBrandon Shaw
First floor only...
BLD-Foundation9/17/20199/17/20199/17/2019PPASS
DetailsBrandon Shaw
Work in progress...
BLD-Footing9/13/20199/13/20199/13/2019PPASS
DetailsBrandon Shaw
2pm if possible Phone #: ###-#### Inspection requested via web by Kyle Seick