Information based on query as of Monday, May 13, 2024.
Permit Information
Permit NumberBLD19-02757
StatusFinaled
Name HHS CONSTRUCTION LLC
Site Address 5960 E HOOTOWL DR
Project NameHarris North Lot 6 Block 2
Customer Number 
ePlanReviewYes
Description
**W.U.I. HILLSIDE ZONE A CLASS "A" ROOF AND NON-COMBUSTIBLE EXTERIOR SIDING REQUIRED** **PRESCRIPTIVE ENERGY REQUIRMENTS** Permit for the construction of a new 2986 sq. ft., one story single family dwelling with 4 bedrooms, 2.5 bathrooms, approximately 311 sq. ft. of covered patio/porch and a 762 sq. ft. attached garage per the approved plans and any notations. SP-01 zoning and setbacks per planning. ***SPRINKLERS ARE NOT REQUIRED*** LGM A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/21/20201/21/20201/21/2020PPASS
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by Kyle Seick
DOC - Permit Finaled1/21/20201/21/20201/21/2020PPASS
DetailsBrandon Shaw
BLD-Final1/17/20201/17/20201/17/2020ANR
DetailsBrandon Shaw
Need PW approval...
BLD-Blower Door Test Results1/17/20201/17/20201/17/2020ADONE
DetailsBrandon Shaw
ACH50- 4.1
BLD-Other10/4/201910/4/201910/4/2019PPASS
DetailsBrandon Shaw
Sheetrock soffit. Phone #: ###-#### Inspection requested via web by Kyle Seick
BLD-Energy code compliance10/1/201910/2/201910/2/2019APASS
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by Kyle Seick
BLD-Framing/Rough-in9/30/20199/30/201910/1/2019PPASS
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by Kyle Seick
BLD-Wall Bracing9/11/20199/11/20199/11/2019PPASS
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Kyle Seick
BLD-Foundation8/19/20198/19/20198/19/2019PPASS
DetailsBrandon Shaw
Work in progress...
BLD-Footing8/16/20198/16/20198/16/2019PPASS
DetailsBrandon Shaw
Work in progress...