BLD-Final | 1/24/2020 | 1/27/2020 | 1/27/2020 | A | PASS |
Brandon Shaw
|
|
|
Final inspection please. John Lattimer will be your contact. Please give him a 30 minute lead time to meet you there. Thank you and have a great day! Phone #: ###-#### Inspection requested via web by Laura Longshaw
|
DOC - Permit Finaled | 1/27/2020 | 1/27/2020 | 1/27/2020 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Final | 1/20/2020 | 1/21/2020 | 1/21/2020 | A | FAIL |
Brandon Shaw
|
|
|
Per R314.3.1 Alteration/ additions and R315 Carbon...
|
BLD-Final | 12/23/2019 | 12/24/2019 | 12/23/2019 | A | CANC |
Brandon Shaw
|
|
|
Final inspection please. Contact is Darius Elison. Please give a 20 minute call ahead. Merry Christmas and Thank you! Phone #: ###-#### >> Inspection requested via web by Laura Longshaw Inspection cancelled from web by: Laura Longshaw
|
BLD-Final | 12/19/2019 | 12/20/2019 | 12/20/2019 | P | NR |
Brandon Shaw
|
|
|
Need Ele final...
|
BLD-Other | 10/18/2019 | 10/22/2019 | 10/22/2019 | P | PASS |
Brandon Shaw
|
|
|
Insulation inspection. Contact is John Lattimer. Thank you and have a great day! Phone #: ###-#### Inspection requested via web by Laura Longshaw
|
BLD-Framing/Rough-in | 10/18/2019 | 10/21/2019 | 10/21/2019 | A | PASS |
Brandon Shaw
|
|
|
OK to insulate...
|
BLD-Framing/Rough-in | 10/14/2019 | 10/14/2019 | 10/14/2019 | P | DEFR |
Brandon Shaw
|
|
|
Framing rough in conference...
|
BLD-Footing | 9/27/2019 | 9/27/2019 | 9/27/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|