BLD-Final | 6/18/2020 | 6/18/2020 | 6/18/2020 | P | PASS |
Mike Jordan
|
|
|
Tyler *screened* Phone #: ###-####
|
DOC - Permit Finaled | 6/18/2020 | 6/18/2020 | 6/18/2020 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 4/22/2020 | 4/22/2020 | 4/22/2020 | P | PASS |
Mike Jordan
|
|
|
Tyler Phone #: ###-####
|
BLD-Framing/Rough-in | 4/16/2020 | 4/16/2020 | 4/16/2020 | P | PEND |
Dave Hannah
|
|
|
Tyler Phone #: ###-####
|
BLD-Framing/Rough-in | 4/13/2020 | 4/13/2020 | 4/13/2020 | P | NR |
Mike Jordan
|
|
|
stated no one should be onsite // Tyler Phone #: ###-####. A mech rough in inspection is required prior to framing inspection. Air seal pack also required to be completed prior to framing inspection.
|
BLD-Wall Bracing | 3/31/2020 | 3/31/2020 | 3/31/2020 | P | PASS |
Mike Jordan
|
|
|
shear // curtis Phone #: ###-####
|
BLD-Wall Bracing | 3/24/2020 | 3/25/2020 | 3/25/2020 | A | FAIL |
Mike Jordan
|
|
|
shear // Tyler Phone #: ###-####. Provide the city set of approved plans. Noted several areas with missing fasteners. Provide 8d hot dipped galvanized nails into sill plate. Correction notice issued.
|
BLD-Foundation | 2/20/2020 | 2/20/2020 | 2/20/2020 | P | PASS |
Mike Jordan
|
|
|
Tyler Phone #: ###-####
|
BLD-Footing | 2/18/2020 | 2/18/2020 | 2/18/2020 | P | PASS |
Mike Jordan
|
|
|
Tyler Phone #: ###-####
|
BLD-Footing | 2/14/2020 | 2/18/2020 | 2/18/2020 | A | FAIL |
Mike Jordan
|
|
|
Tyler Phone #: ###-####. No one on site. No city approved plans on site. Also noted at time of inspection form work and footing subgrade are frozen.
|