BLD-Wall Bracing | 7/7/2020 | 7/8/2020 | 7/8/2020 | A | PASS |
Mike Jordan
|
|
|
Shawn *screened* Phone #: ###-####
|
BLD-Wall Bracing | 7/6/2020 | 7/7/2020 | 7/7/2020 | A | NR |
Mike Jordan
|
|
|
shear // Shawn SCREENED Phone #: ###-####
|
BLD-Framing/Rough-in | 6/23/2020 | 6/24/2020 | 6/24/2020 | A | PASS |
Mike Jordan
|
|
|
screened // 2 hour firewall // Shawn Phone #: ###-####. Base layer, 1st. floor.
|
BLD-Foundation | 6/9/2020 | 6/9/2020 | 6/9/2020 | P | PASS |
Mike Jordan
|
|
|
Shawn Phone #: ###-####
|
BLD-Footing | 6/8/2020 | 6/8/2020 | 6/8/2020 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by James Jewett
|
BLD-Foundation | 6/8/2020 | 6/8/2020 | 6/8/2020 | P | CANC |
Mike Jordan
|
|
|
Shawn - 2pm pour time Phone #: ###-####
|
BLD-Footing | 6/6/2020 | 6/8/2020 | 6/8/2020 | A | FAIL |
Mike Jordan
|
|
|
8:00 am Phone #: ###-#### Inspection requested via web by James Jewett. No plans on site.
|