Final | 2/12/2019 | 2/14/2019 | 2/14/2019 | P | PASS |
Mark Moncarr
|
|
|
###-#### Aaron. Re-scheduled from tue 12th. Ok final. All recepts that I could get too were TR, and spark rings were not needed. ARC fault protection is in place.
|
Final | 2/11/2019 | 2/12/2019 | 2/12/2019 | A | CANC |
Mark Moncarr
|
|
|
Steve-Eric you may not need to go herebecause you finaled this but it did not close the case can you please doc final. if you need to go out there please call Steve Phone #: ###-#### Talked to homeowner. Re-scheduled for the 14th
|
Electrical Rough-In | 3/28/2016 | 3/28/2016 | 3/28/2016 | P | PASS |
Eric Story
|
|
|
owner will remove receptacles for install of sheetrock and will install chases to protect type nm cable basement rooms ok cover
|
Final | 3/28/2016 | 3/28/2016 | 3/28/2016 | P | PASS |
Eric Story
|
|
|
Aaron-as early as possible-bldg to be done PM Late Phone #: ###-#### needed rough-in
|
Conference | 3/14/2016 | 3/15/2016 | 3/15/2016 | P | DONE |
Eric Story
|
|
|
Aaron// please call before Phone #: ###-#### discussed wiring methods and code requierments for addition to bedrooms in basement and living room
|