Final | 3/26/2019 | 3/27/2019 | 3/27/2019 | A | PASS |
James Ady
|
|
|
Jade Phone #: ###-#### Final ok
|
Final | 3/20/2019 | 3/20/2019 | 3/20/2019 | P | NR |
James Ady
|
|
|
Jay Phone #: ###-####
|
Electrical Rough-In | 6/27/2018 | 6/28/2018 | 6/28/2018 | A | PASS |
James Ady
|
|
|
Inspection requested via web by jade jasper SE underground ok to cover
|
Electrical Rough-In | 6/14/2018 | 6/15/2018 | 6/15/2018 | A | PASS |
James Ady
|
|
|
Phone #: ###-#### Inspection requested via web by jade jasper Underground from New building to 2 light poles Ok to cover
|
Electrical Rough-In | 6/12/2018 | 6/13/2018 | 6/13/2018 | P | PASS |
James Ady
|
|
|
Phone #: ###-#### Inspection requested via web by jade jasper south side of parking lot, 3 lights only ok to cover
|
Electrical Rough-In | 6/12/2018 | 6/12/2018 | 6/12/2018 | P | CANC |
James Ady
|
|
|
Phone #: ###-#### Inspection requested via web by jade jasper rescheduled for 6/13/18 pm
|