Final | 4/23/2019 | 4/24/2019 | 4/24/2019 | P | PASS |
Tom Saunders
|
|
|
Please call Ben Culp before hand, and he will meet you on site. Phone #: ###-#### Inspection requested via web by Jeremy Cloud... correction made...ok to final
|
Final | 4/22/2019 | 4/23/2019 | 4/23/2019 | P | FAIL |
Tom Saunders
|
|
|
Please contact Ben Culp before hand, he will meet you there. Phone #: ###-#### Inspection requested via web by Jeremy Cloud.. 1) LV rack needs bonded..min #6 2) no circuit shall draw more than 80% of load..upper break rm counter outlet, D/W, disposal, and bathroom all on one circuit
|
Final | 4/19/2019 | 4/23/2019 | 4/22/2019 | A | CANC |
Tom Saunders
|
|
|
Please call when on your way and Ben will meet you there. Phone #: ###-#### >> Inspection requested via web by Jeremy Cloud Inspection cancelled from web by: Jeremy Cloud
|
Electrical Rough-In | 3/28/2019 | 3/29/2019 | 3/29/2019 | A | PASS |
Tom Saunders
|
|
|
Inspect bathroom ceilings for cover. Phone #: ###-#### Inspection requested via web by Jeremy Cloud... ok to cover
|
Electrical Rough-In | 2/4/2019 | 2/5/2019 | 2/5/2019 | A | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Cloud...vestibule ok to cover..verify htr circuit at final-blanked of
|
Electrical Rough-In | 1/10/2019 | 1/11/2019 | 1/11/2019 | A | PASS |
Tom Saunders
|
|
|
Phone room wall rough in Phone #: ###-#### Inspection requested via web by Jason Parke... rough ok to cover
|
Electrical Rough-In | 1/8/2019 | 1/9/2019 | 1/9/2019 | A | PASS |
Tom Saunders
|
|
|
Riser room walls and discuss auxiliary gutter at panel Phone #: ###-#### Inspection requested via web by Jason Parke... riser room ok to cover
|
Electrical Rough-In | 1/8/2019 | 1/8/2019 | 1/8/2019 | P | PASS |
Tom Saunders
|
|
|
Second floor offices wall rough in Phone #: ###-#### Inspection requested via web by Jason Parke... wall cover 2nd floor ok
|
Electrical Rough-In | 1/3/2019 | 1/4/2019 | 1/4/2019 | P | PASS |
Tom Saunders
|
|
|
First floor office area walls- cover Phone #: ###-#### Inspection requested via web by Jason Parke... 1st floor offices and main open area walls ok to cover
|
Electrical Rough-In | 12/18/2018 | 12/19/2018 | 12/19/2018 | A | PASS |
Tom Saunders
|
|
|
Inspect walls for cover. Phone #: ###-#### Inspection requested via web by Jeremy Cloud..
cover for exterior wall of riser room...moving switches and wiring for exterior signs GC on job has onesided walls...says all electrical will be ran under 4ft...told to stop as well as the building inspector...will remove for future inspections as needed
|
Electrical Rough-In | 11/8/2018 | 11/9/2018 | 11/9/2018 | P | PASS |
Tom Saunders
|
|
|
Inspect underground for cover. Site contact is John Nate ###-####. Phone #: ###-#### Inspection requested via web by Jeremy Cloud... ok to cover
|