Final | 5/9/2019 | 5/9/2019 | 5/9/2019 | P | PASS |
Rock A. Hudson
|
|
|
PLEASE CALL ONE HOUR BEFORE SO WE CAN MEET YOU ON-SITE: ###-#### Phone #: ###-#### Inspection requested via web by Rob Maes Final ok
|
Final | 4/30/2019 | 4/30/2019 | 4/30/2019 | P | CANC |
Tom Saunders
|
|
|
Please call Preston Saey, the electrician, one hour before arriving on site so he can meet you there. ###-#### Phone #: ###-#### >> Inspection requested via web by Rob Maes Inspection cancelled from web by: Rob Maes
|
Electrical Rough-In | 4/26/2019 | 4/26/2019 | 4/26/2019 | A | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Rob Maes... conference on hooking up house solar to unused disconnect in garage to make connection to ID Powere feeds ok
|
Electrical Rough-In | 4/24/2019 | 4/24/2019 | 4/24/2019 | P | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Rob Maes... unground feeding power and returning solar power at/from detached building-ok grounding and panel at detached shop-ok junction box on exterior house bonding and grounding ok connection of solar at house shall not be made at disconnect in garage...will need to be made in CT can/gutter with ID Power's approval...hole in CT can/gutter needs addressed job forman (Preston) is required to be present at FINAL to go over completed work with inspector
|
Electrical Rough-In | 4/22/2019 | 4/23/2019 | 4/23/2019 | P | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Rob Maes... UL listed equipment verified future rough in inspection will need scheduled for underground and new plans acceptance from Boise City
|