Site Final | 8/6/2018 | 8/6/2018 | 8/6/2018 | P | DONE |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 8/6/2018 | 8/6/2018 | 8/6/2018 | P | PASS |
Mike Jordan
|
|
|
|
General Inspection | 6/26/2018 | 6/26/2018 | 6/26/2018 | | PASS |
Michael Zawacki
|
|
|
Building exterior and disturbance nearly complete. ETA for finish is July 14th. Landscaping done and fabric installed, still needs top coverage. Area will be swept once work in complete and trailers and boxes removed. Will follow up after completion date to check for clean up.
|
General Inspection | 5/11/2018 | 5/11/2018 | 5/11/2018 | | CANC |
Michael Zawacki
|
|
|
|
General Inspection | 3/26/2018 | 3/26/2018 | 3/26/2018 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 2/7/2018 | 2/7/2018 | 2/7/2018 | | PASS |
Michael Zawacki
|
|
|
Site contained. Softball season set to begin, contractor will have to rearrange site and switch entrances. They plan on having everything done by the 15th.
|
General Inspection | 12/19/2017 | 12/19/2017 | 12/19/2017 | | PASS |
Michael Zawacki
|
|
|
All excavation and concrete completed for time being. Site is clean and trash free. No dirt leaving site.
|
General Inspection | 11/1/2017 | 11/1/2017 | 11/1/2017 | | PASS |
Michael Zawacki
|
|
|
Perimeter controls intact and working. No fugitive dust or dirt. Site free of trash. Currently no concrete washouts, foreman said they had eco pans and will have them again for the next pour. DIs clean and maintained.
|