General Inspection | 3/2/2020 | 3/2/2020 | 3/2/2020 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 3/2/2020 | 3/2/2020 | 3/2/2020 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 1/14/2020 | 1/14/2020 | 1/14/2020 | | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 11/29/2019 | 11/29/2019 | 12/2/2019 | | PASS |
Michael Zawacki
|
|
|
Exterior work completed, site clean. To much snow and slush to see if DI protection still installed.
|
General Inspection | 10/14/2019 | 10/14/2019 | 10/14/2019 | | CANC |
Michael Zawacki
|
|
|
|
General Inspection | 8/26/2019 | 8/27/2019 | 8/30/2019 | P | PASS |
Andy J. Long
|
|
|
Project near completion. No trackout, loose trash around site, or discharges observed
|
General Inspection | 8/23/2019 | 8/23/2019 | 8/26/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 7/8/2019 | 7/8/2019 | 7/12/2019 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 5/17/2019 | 5/17/2019 | 5/23/2019 | | PASS |
Andy J. Long
|
|
|
|
Site Final | 5/20/2019 | 5/21/2019 | 5/20/2019 | P | CANC |
Andy J. Long
|
|
|
|
General Inspection | 4/1/2019 | 4/1/2019 | 4/1/2019 | | PASS |
Andy J. Long
|
|
|
No trackout. Clean site. Storm drains have sediment protection.
|
General Inspection | 2/12/2019 | 2/12/2019 | 2/12/2019 | | PASS |
Andy J. Long
|
|
|
No trackout or discharges. Staging area and project area is clean with no loose trash or debris. Storm drains have sediment protection. Vertical construction in progress.
|
General Inspection | 12/28/2018 | 12/28/2018 | 12/28/2018 | | PASS |
Michael Zawacki
|
|
|
WIP on vertical. Site is contained, no ESC issues.
|
General Inspection | 11/12/2018 | 11/12/2018 | 11/13/2018 | | PASS |
Andy J. Long
|
|
|
No trackout, discharges, or loose trash/debris around perimter. Storm drain on 9th is currently being retrofitted.
|
General Inspection | 9/27/2018 | 9/27/2018 | 9/27/2018 | P | PASS |
Andy J. Long
|
|
|
Vertical construction in progress. Perimeter is clean, no trackout, discharges, or loose materials. Storm drains have sediment protection. Approved.
|
General Inspection | 8/29/2018 | 8/29/2018 | 8/29/2018 | P | PASS |
Michael Zawacki
|
|
|
All DIs surrounding area protected. Seepage beds are already completed and will hold all stormwater. Workers cleaning all loose trash when I arrived. No ESC issues.
|
General Inspection | 7/27/2018 | 7/27/2018 | 7/27/2018 | P | PASS |
Andy J. Long
|
|
|
Vertical construction in progress. No trackout, discharges, or loose material in streets & gutters around site. DIs have sediment protection.
|
General Inspection | 5/30/2018 | 6/12/2018 | 6/13/2018 | P | PASS |
Michael Zawacki
|
|
|
Project has left lane of 9th street closed, job access is from Fulton Street. Concrete work has begun, kiddie pool in use for washout. No dirt is leaving site, no blowing dust at time of inspection. All material stored within fenced area, large dumpster on site, area free from trash.
|
General Inspection | 5/29/2018 | 5/30/2018 | 5/30/2018 | A | PASS |
Andy J. Long
|
|
|
No trackout from site. Track out observed 5/29 on River has been swept. No discharges or other violations. Approved.
|
General Inspection | 4/12/2018 | 4/12/2018 | 4/13/2018 | P | PASS |
Michael Zawacki
|
|
|
Some track out onto River & 9th, talked to foreman and they have sweepers every few hours. Lot is being watered to keep dust down, DIs are protected. No other issues besides trackout.
|
General Inspection | 4/5/2018 | 4/6/2018 | 4/12/2018 | A | CANC |
Andy J. Long
|
|
|
|
Tracking Control | 3/15/2018 | 3/15/2018 | 3/15/2018 | P | PEND |
Andy J. Long
|
|
|
Site is muddy with unmaintained rock entrance. Sidewalk and left lane of 9th street have trackout
Corrections needed to reduce trackout:
- install new construction rock. 1.5-3" angular or crushed rock -sweep sidewalk and apron on 9th street
RP agreed to clean up today and request more rock.
|
Site Preparation | 2/26/2018 | 2/27/2018 | 2/27/2018 | P | PASS |
Andy J. Long
|
|
|
1 PM site walk through
MS4 storm drains on 9th Street and on River Street have been fitted with new inlet sediment protection. Two construction entrances are installed for initial excavation phase. Requested that apron be checked every day to sweep sidewalk and make sure rocks are not in traffic lanes.Requested next rock needs to be angular. Employee parking and job trailer with SWPPP are located north of the site on corner of 9th Street and Fulton. Existing asphalt to be preserved.
Trash dumpster in staging yard, concrete washouts will be portable plastic containers placed in staging yard and around site for easy access.
Site to be inspected 2x monthly. ESC permit signs to be posted in job trailer and along fence on River Street.
|
Site Preparation | 2/22/2018 | 2/26/2018 | 2/26/2018 | P | CANC |
Andy J. Long
|
|
|
rescheduled
|
Site Preparation | 2/21/2018 | 2/22/2018 | 2/22/2018 | P | CANC |
Andy J. Long
|
|
|
rescheduled due to snow cover, RP Jason to call next week
|