Permit Information
Permit NumberESC19-00861
StatusFinaled
Name JOHN KAMINSKI
Site Address 951 E GOWEN RD
Project NameRED RIVER-93 ACRE DEVELOPMENT
Customer Number 
ePlanReviewNo
Description
This project consists of the re-alignment of 3,500 linear feet of Fivemile Creek
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final1/17/20201/17/20201/21/2020PPASS
DetailsMichael Zawacki
Grading final requested, GRD19-00049. Info sent to Jason Taylor.
Tracking Control12/16/201912/18/201912/20/2019PPASS
DetailsAndy J. Long
Construction entrance extended and more rock placed. Still some trackout. Need to clean up clods out of road.
General Inspection12/13/201912/13/201912/16/2019PFAIL
DetailsAndy J. Long
Construction entrance is small gravel rock, not larger angular rock. Entrance needs to be extended. Recommend over 75 feet. Very muddy conditions on cut road into site. Should consider putting road mix down and designate parking areas out of mud.
General Inspection11/1/201911/1/201911/6/2019PPASS
DetailsMichael Zawacki
Realigning creek started from north working sw through site. New channel is defined, more in the northern section of site. Some rock armoring has been installed on curves. Evidence of sprayed water for compaction. Strip of land grubbed parrallel to creek, most of site still has natural cover. No esc issues, work area is isolated.
Site Preparation10/15/201910/15/201910/16/2019PPASS
DetailsMichael Zawacki
ork has begun on creek channel. Entrance is on south of old Fred Meyer distro.
Gravel entrance, work is a few hundred yards back. Lots of vegetation on site. Will not need to haul away striped material. Water truck on site, needs to cross Gowen to fill.