INSP-Final Inspection | 12/16/2011 | 12/16/2011 | 1/24/2012 | P | PASS |
Forrest France
|
|
|
George Phone #: ###-####
|
INSP-Final Inspection | 12/23/2011 | 12/23/2011 | 12/23/2011 | A | PASS |
Forrest France
|
|
|
Remainder of correction items verified. Fire sprinkler permit finaled.
|
INSP-Sprinkler Rough-in | 10/27/2011 | 10/27/2011 | 10/27/2011 | P | PART |
Forrest France
|
|
|
Overhead work at the drop ceiling corridor 1st floor building #2 okayed for cover.
|
INSP-Sprinkler Rough-in | 9/23/2011 | 9/26/2011 | 9/26/2011 | A | PART |
Forrest France
|
|
|
Trip testing per NFPA 13 completed for building # 2 second and fourth floor dry systems.
|
INSP-Sprinkler Rough-in | 9/12/2011 | 9/12/2011 | 9/12/2011 | P | PART |
Forrest France
|
|
|
Noted obstructed heads at several locations throughout the parking garage level by adjacent light fixtures, plumbing and mechanical pipe, electrical conduit, etc.
|
INSP-Sprinkler Rough-in | 9/12/2011 | 9/12/2011 | 9/12/2011 | P | PART |
Forrest France
|
|
|
Trip testing for both building 2 and 3 dry system parking garage levels per NFPA 13 24.2.3.2.1 completed satisfactory.
|
INSP-Sprinkler Rough-in | 9/8/2011 | 9/9/2011 | 9/9/2011 | A | PART |
Forrest France
|
|
|
Pendent heads at the 2nd, 3rd and 4th floor corridors of building three approved for cover.
|
INSP-Sprinkler Rough-in | 8/26/2011 | 8/26/2011 | 8/29/2011 | P | PART |
Forrest France
|
|
|
Verified trash chute protection at building #2 and #3 2nd and 4th floors.
|
INSP-Sprinkler Rough-in/Hydro | 8/22/2011 | 8/23/2011 | 8/25/2011 | A | PART |
Forrest France
|
|
|
Pneumatic testing for the two basement dry systems, dry standpipe, and both buildings #2 and #3 2nd and 4th floor level dry systems completed satisfactory per NFPA 13 requirements.
|
INSP-Sprinkler Rough-in | 8/22/2011 | 8/22/2011 | 8/22/2011 | P | PART |
Forrest France
|
|
|
Begin 24 hr. air test of the new dry systems at all floor levels for both buildings #2 and 3 @3:00PM.
|
INSP-Sprinkler Rough-in/Hydro | 8/18/2011 | 8/19/2011 | 8/19/2011 | A | DONE |
Tim Frost
|
|
|
Hydro passed on east side for
4th floor
3rd floor
2nd floor
Basement (2) dry system and fdc. (Did not do the main)
-TRF-
jeremy Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 8/16/2011 | 8/17/2011 | 8/17/2011 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic test for the 4th floor dry system building #2 passed.
|
INSP-Sprinkler Rough-in/Hydro | 8/16/2011 | 8/16/2011 | 8/16/2011 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic testing for building #2 2nd, 3rd, and 4th floor wet systems passsed.
|
INSP-Sprinkler Rough-in/Hydro | 8/10/2011 | 8/11/2011 | 8/12/2011 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic test for the dry system 2nd floor building #2 passed.
|
INSP-Sprinkler Rough-in/Hydro | 8/9/2011 | 8/9/2011 | 8/10/2011 | P | PART |
Forrest France
|
|
|
Completed hydrostatic testing of both building #2 and building #3 1st floor antifreeze systems.
|
INSP-Sprinkler Rough-in | 8/3/2011 | 8/4/2011 | 8/4/2011 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for my initials and todays date for apartments where the piping to the sprinkler drops can be covered and at the garbage shutes where the piping can be covered.
|
INSP-Sprinkler Rough-in | 7/27/2011 | 7/27/2011 | 7/27/2011 | A | PART |
Forrest France
|
|
|
Reference dated plan annotations.
|
INSP-Sprinkler Rough-in | 7/20/2011 | 7/21/2011 | 7/21/2011 | P | PART |
Forrest France
|
|
|
Third floor building #2 sheetrock lids and soffits okay for cover. Minor adjustments made while on site.
|
INSP-Sprinkler Rough-in | 7/20/2011 | 7/20/2011 | 7/21/2011 | A | PART |
Forrest France
|
|
|
Jeremy phone #: ###-####
|
INSP-Sprinkler Rough-in | 7/19/2011 | 7/19/2011 | 7/19/2011 | P | PART |
Forrest France
|
|
|
Regarding sprinkler coverage at the top of stairways in buildings 2 and 3.
|
INSP-Sprinkler Rough-in | 7/15/2011 | 7/15/2011 | 7/15/2011 | P | PART |
Forrest France
|
|
|
Okayed for cover amenity rooms, restrooms and concealed space adjacent to the electrical room- noted and marked with today's date.
|
INSP-Sprinkler Rough-in | 7/12/2011 | 7/12/2011 | 7/12/2011 | P | PART |
Forrest France
|
|
|
Ref. dated plan annotations.
|
INSP-Sprinkler Rough-in | 7/11/2011 | 7/12/2011 | 7/12/2011 | A | PART |
Forrest France
|
|
|
Units A2 and D2 4th floor building #2 okayed for cover at the sheetrock soffits. Also noted on plans areas on the 1st floor buildings# 2 and 3 approved for cover including restrooms, breakroom/kitchen, common area- marked with todays date.
|
INSP-Sprinkler Rough-in | 7/5/2011 | 7/6/2011 | 7/6/2011 | A | PART |
Forrest France
|
|
|
4th floor building #3 units F1, E1 and E2 sheetrock lid soffits okayed for cover.
|
INSP-Sprinkler Rough-in | 6/28/2011 | 6/29/2011 | 6/29/2011 | A | PART |
Forrest France
|
|
|
See plans for areas on 1st thru 4th floors building #3 inspected today for cover approval. Noted locations in need of adjustment.
|
INSP-Sprinkler Rough-in | 6/28/2011 | 6/28/2011 | 6/28/2011 | P | CANC |
Forrest France
|
|
|
Overbooked
|
INSP-Sprinkler Rough-in | 6/15/2011 | 6/15/2011 | 6/15/2011 | A | PART |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 6/13/2011 | 6/14/2011 | 6/14/2011 | A | PART |
Forrest France
|
|
|
Inspection for cover at 3rd floor building #3 tenant units only okayed with exceptions in unit 304 as marked on plan set. Also inspected coverage/ non-combustible finishes at 1st thru 4th floor concealed spaces behind and above fireplace enclosures. Note, some locations are sprinklered and others are sheetrocked to meet allowable exceptions per NFPA 13. Also noted 1st floor blind space room adjacent the the electrical room building #2 SW corner to be sprinklered.
|
INSP-Sprinkler Rough-in | 6/9/2011 | 6/9/2011 | 6/10/2011 | P | CANC |
Troy Cobbley
|
|
|
Canceled due to time constraints. Per Lonnie this will be rescheduled for Monday Phone #: ###-####
|
INSP-Sprinkler Rough-in | 5/31/2011 | 6/1/2011 | 6/2/2011 | A | PART |
Forrest France
|
|
|
Overhead inspection for 2nd floor building #2 units D (east and west), A2, B2, C, C2, and D1 completed. Items noted on plan include seven unprotected concealed spaces at units D, B2 and D1, missing heads per plan at bathrooms units A2 and B2. Also noted pipe size discrepancies between field install and approved plan at A2- need to match plan or provide design info to support changes.
|
INSP-Sprinkler Rough-in | 5/25/2011 | 5/25/2011 | 6/1/2011 | A | PART |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 6/1/2011 | 6/1/2011 | 6/1/2011 | P | FAIL |
Forrest France
|
|
|
Inspection for cover at the 2nd floor building #2 incomplete due to significant field modifications in branch line locations/pipe sizes which differ from the approved design.
|
INSP-Sprinkler Rough-in | 5/20/2011 | 5/20/2011 | 5/27/2011 | P | PART |
Forrest France
|
|
|
Ref. plan set for dated annotations (5/19) building #2 for rough-in at portions of 2nd floor units okayed to cover.
|
INSP-Sprinkler Rough-in | 5/26/2011 | 5/26/2011 | 5/26/2011 | P | PART |
Forrest France
|
|
|
OH piping at building #3 east stairway floors basement thru 3rd floor okayed for cover.
|
INSP-Sprinkler Rough-in | 5/10/2011 | 5/10/2011 | 5/12/2011 | A | PART |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 5/9/2011 | 5/9/2011 | 5/9/2011 | P | PART |
Forrest France
|
|
|
Site visit to verify insulation fill at building #3 second floor non-sprinklered eaves (6 locations).
|
FIR-Aging Inspection | 3/11/2011 | 3/11/2011 | 3/15/2011 | | DONE |
Forrest France
|
|
|
Construction suspended.
|
FIR-Aging Inspection | 12/28/2010 | 12/28/2010 | 12/28/2010 | | DONE |
Forrest France
|
|
|
Construction suspended.
|
FIR-Aging Inspection | 10/28/2010 | 10/28/2010 | 10/28/2010 | | DONE |
Forrest France
|
|
|
See activity note dated 8/19.
|
FIR-Aging Inspection | 8/19/2010 | 8/19/2010 | 8/19/2010 | | DONE |
Forrest France
|
|
|
Construction suspended.
|
FIR-Aging Inspection | 6/17/2010 | 6/17/2010 | 6/23/2010 | | DONE |
Forrest France
|
|
|
Construction suspended.
|
INSP-Sprinkler Rough-in/Hydro | 11/4/2008 | 11/5/2008 | 11/5/2008 | A | PART |
Forrest France
|
|
|
Inspection to verify non-sprinklered concealed attic pockets at the 2nd floor east side are entireley filled with non-combustible insulation to meet exception requirements per NFPA 13 as discussed.
|
INSP-Sprinkler Rough-in/Hydro | 10/29/2008 | 10/30/2008 | 10/30/2008 | A | FAIL |
Forrest France
|
|
|
Insulation at the concealed non-sprinklered attic pockets is still missing, will need inspection prior to cover approval.
|
INSP-Sprinkler Rough-in/Hydro | 10/29/2008 | 10/29/2008 | 10/29/2008 | A | NR |
Forrest France
|
|
|
Insulation at the non-sprinklered attic spaces is not yet completed for inspection.
|
INSP-Sprinkler Rough-in/Hydro | 10/27/2008 | 10/28/2008 | 10/28/2008 | P | PART |
Forrest France
|
|
|
Building #3 2nd floor wet and dry system rough-in inspections passed with the exception of 5 concealed combustible attic pockets in need of sprinkler protection-or to be filled entirely with insulation per NFPA 13 exceptions including 2 pockets at the dry system, also noted one upright head to be relocated due to truss obstructions. See annotations on stamped plan set for locations.
|
INSP-Sprinkler Rough-in/Hydro | 10/22/2008 | 10/23/2008 | 10/23/2008 | P | PART |
Forrest France
|
|
|
OH rough-in for the 4th floor building #2 wet and dry system inspection completed today, noted one missing upright head at the attic system above the riser room, missing seismic bracing at dry system mains north side, tenting at the wet piping appears acceptable. Noted corridors, laundry/trash chute rooms, and star landings are not yet complete, field modifications annotated on plans for added or deleted heads, attic pockets at the north end to be entirely filled with non-combustible insulation to meet exception criteria per NFPA 13 for non-sprinklered locations.
|
INSP-Sprinkler Rough-in/Hydro | 10/13/2008 | 10/13/2008 | 10/13/2008 | P | PART |
Forrest France
|
|
|
See approved plans for locations inspected to date.
|
INSP-Sprinkler Rough-in/Hydro | 9/23/2008 | 9/24/2008 | 9/24/2008 | A | PART |
Forrest France
|
|
|
See areas on 3rd floor plan marked with today's date, noted two missing hangers, need EC coverage SW heads at the patios due to spacing (head legend does not indicate), pipe sizes on plan must match field install.
|
INSP-Sprinkler Rough-in/Hydro | 9/22/2008 | 9/23/2008 | 9/23/2008 | A | PART |
Forrest France
|
|
|
Inspection for C/N items on the 4th floor per notes 9/22 completed acceptable.
|
INSP-Sprinkler Rough-in/Hydro | 9/19/2008 | 9/22/2008 | 9/22/2008 | A | FAIL |
Forrest France
|
|
|
See areas on approved plan for locations inspected today and items in need of revision at the dry system and 4th floor wet system west side. Noted two missing EQ braces, one blocked upright head, two heads exceeding min. spacing, one overspaced pendent, exterior balconies and patios are not protected, tenting at some locations needs adjusted, field changes at the lobby, stair and elevator hoistway need to be shown on as-built drawings, two noted concealed spaces must be non-combustible or protected.
|
INSP-Sprinkler Rough-in/Hydro | 9/19/2008 | 9/19/2008 | 9/19/2008 | P | PART |
Forrest France
|
|
|
1st floor correction notice items per last inspection okayed with the exception of plans reflecting actual install, discussed next site visit for rough-in work to date.
|
INSP-Sprinkler Rough-in | 9/10/2008 | 9/11/2008 | 9/15/2008 | A | PART |
Forrest France
|
|
|
See locations on approved plan set sheet FP5 for locations inspected to date on the 1st floor only, including areas north of the corridor main, noted issues in need of revision clouded and annotated.
|
INSP-Sprinkler Rough-in | 7/22/2008 | 7/23/2008 | 7/23/2008 | A | FAIL |
Troy Cobbley
|
|
|
The first floor plans do not match the installation. No of the piping shown on the basement plans had sizing. Bracing was not complete on the standpipes. Basically no inspection was performed.
|
INSP-Sprinkler Rough-in | 9/22/2011 | 9/22/2011 | | P | |
Forrest France
|
|
|
lonnie Phone #: ###-####
|