FIR-Aging Inspection | 4/25/2018 | 4/25/2018 | 4/27/2018 | | NR |
Troy Cobbley
|
|
|
This permit will need to be voided due to another contractor is taken over the work.
|
FIR-Aging Inspection | 9/25/2017 | 9/25/2017 | 9/25/2017 | | NR |
Troy Cobbley
|
|
|
Waiting for fire dept. follow up and contractor to call for final inspection
|
FIR-Aging Inspection | 5/8/2017 | 5/8/2017 | 5/8/2017 | | NR |
Troy Cobbley
|
|
|
Waiting on fire dept follow up
|
FIR-Aging Inspection | 10/26/2016 | 10/26/2016 | 11/1/2016 | | NR |
Troy Cobbley
|
|
|
I turned this over to the fire dept for follow up
|
FIR-Aging Inspection | 7/27/2016 | 7/27/2016 | 7/27/2016 | | NR |
Troy Cobbley
|
|
|
I spoke to Assistant Chief Ron Johnson about a previous request for help.
|
INSP-Conference | 3/11/2016 | 3/11/2016 | 3/11/2016 | P | DONE |
Troy Cobbley
|
|
|
Wendy contacted me and stated that Peak Alarm is no longer in a business arrangement with the building owner. I spoke to Scott and have forwarded information to Chief Gervais with the Fire Dept.
|
FIR-Aging Inspection | 3/7/2016 | 3/7/2016 | 3/11/2016 | | NR |
Troy Cobbley
|
|
|
I left a voice message for Wendy the Office Manager requesting that the project be finished up.
|
INSP-Final Inspection | 11/7/2013 | 11/8/2013 | 11/8/2013 | A | FAIL |
Troy Cobbley
|
|
|
Began inspection by verifying the sync of the audio/visual devices. When testing the horns on most of the first floor and the west half of the second floor failed to work. Inspection stopped and no devices tested.
|
FIR-Aging Inspection | 10/28/2013 | 10/28/2013 | 10/29/2013 | | NR |
Troy Cobbley
|
|
|
I left message for Mike requesting project status
|
FIR-Aging Inspection | 9/4/2012 | 9/4/2012 | 9/12/2012 | | NR |
Troy Cobbley
|
|
|
I spoke to Jason and Mike and they were going to follow up on this project.
|
INSP-Final Inspection | 4/18/2011 | 4/20/2011 | 4/20/2011 | P | FAIL |
Troy Cobbley
|
|
|
Neither the strobes or the horn were syncronized. Also need to test all initiating devices. Candella needs to be modified to 110cd on the strobe in the old engineering office. End of Line voltage was verified ok as well as spacing of the manual pull stations and audio/visual devices. Netcon was also verified at 5.
|
FIR-Aging Inspection | 4/18/2011 | 4/18/2011 | 4/19/2011 | | NR |
Troy Cobbley
|
|
|
wip
|
INSP-Final Inspection | 2/3/2011 | 2/4/2011 | 2/4/2011 | P | CANC |
Troy Cobbley
|
|
|
Per Mike madsen and my discussion this inspection will be rescheduled for next week.
|
FIR-Aging Inspection | 1/17/2011 | 1/17/2011 | 1/24/2011 | | NR |
Troy Cobbley
|
|
|
wip
|
FIR-Aging Inspection | 11/15/2010 | 11/15/2010 | 11/17/2010 | | NR |
Troy Cobbley
|
|
|
Mike stated that this should be set up for inspection the week after Thanksgiving.
|
INSP-Final Inspection | 4/1/2009 | 4/2/2009 | 4/2/2009 | A | FAIL |
Troy Cobbley
|
|
|
Plans need to be resubmitted for "plan modifications". This is due to extensive audio/visual modifications required such as additional devices, relocated devices and devices that need the candella adjusted brighter. Also the second floor tenant "ABC Channell 6" has a door magnet securing the exit door. The fire alarm contractor and I spoke about minimum sound requirements in the radio transmission rooms where only strobes had been installed and for all rooms. No devices were actually tested. An EOL had to be relocated in the NAC panel so that it would report a trouble
|
INSP-Conference | 1/12/2009 | 1/12/2009 | 1/12/2009 | P | DONE |
Troy Cobbley
|
|
|
I left a message for Mark Cleverly with Thornton Ovliver that we were assured on 12/8/08 the alarm system installation would proceed. I visited the job site and found the alarm system still not functional and the building occupied. I contacted Mike with Peak Alarm and he stated that they would have the PIV connected today and then they would be waiting on phone lines and the elevator. Per the elevator contractor they are atleast three week out. I told Mike that the fire alarm system needs to be up and running. He was going to contact his boss and verify when phone lines would be installed.
|
FIR-Aging Inspection | 11/26/2008 | 11/26/2008 | 12/1/2008 | | NR |
Troy Cobbley
|
|
|
I contacted peak alarm and they said that they would be on the job at the end of December or January as per their contact. I said "so this building has a non-functioning fire alarm system?" And they said yes.
I have forwarded this information to sam rogers and mark sentenno for further action.
|