INSP-Final Inspection | 1/11/2011 | 1/12/2011 | 1/12/2011 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 1/10/2011 | 1/11/2011 | 1/11/2011 | P | CANC |
Troy Cobbley
|
|
|
Please call Guy at ###-#### with inspection time. Phone #: ###-#### >> Inspection requested via web by Lori Brungardt Inspection cancelled from web by: Lori Brungardt
|
INSP-Final Inspection | 1/7/2011 | 1/7/2011 | 1/7/2011 | P | CANC |
Troy Cobbley
|
|
|
CARISSA had not corrdinated with Alarmco to perform this inspection. Will need to be rescheduled.
|
INSP-Final Inspection | 12/30/2010 | 1/3/2011 | 1/3/2011 | A | FAIL |
Troy Cobbley
|
|
|
To final this permit both flow switches and both PIV tamper switches need to be tested. The inspector test lines do not have the required orfice mounted therefore a test or these devices could not be completed.
|
FIR-Aging Inspection | 10/28/2010 | 10/28/2010 | 10/28/2010 | | NR |
Troy Cobbley
|
|
|
Work is in progress. Per Guy all of these AES inspections are being called in shortly.
|
FIR-Aging Inspection | 7/7/2010 | 7/7/2010 | 7/7/2010 | | NR |
Troy Cobbley
|
|
|
Per Bill the AES inspection scheduling is being addressed.
|
INSP-Final Inspection | 4/5/2010 | 4/5/2010 | 4/5/2010 | P | FAIL |
Troy Cobbley
|
|
|
The AES panel had a Netcon 5. The AES panel was being used as a stand alone facp which is not allowed due to listing. The city approved drawings showed a separate facp connected to the new AES panel. No testing other than the Netcon was performed.
|
INSP-Final Inspection | 4/2/2010 | 4/5/2010 | 4/5/2010 | A | FAIL |
Troy Cobbley
|
|
|
I spoke to Bryan at 7:43 to meet with him first thing. I waited at the project site until 8:15. There was no answer on his phone when I tried to re-contact him. No inspection was performed.
|
FIR-Aging Inspection | 5/27/2009 | 5/27/2009 | 5/27/2009 | | NR |
Troy Cobbley
|
|
|
work is in progress
|