INSP-Final Inspection | 11/16/2012 | 11/16/2012 | 11/16/2012 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 11/13/2012 | 11/14/2012 | 11/14/2012 | A | FAIL |
Troy Cobbley
|
|
|
Prior to a final for this permit the ceiling and related pendant sprinkler protection needs to be installed in the two electrical rooms.
|
INSP-Sprinkler Rough-in | 11/13/2012 | 11/13/2012 | 11/13/2012 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations where piping above lay-in ceiling tiles can be covered.
|
INSP-Sprinkler Rough-in | 10/23/2012 | 10/23/2012 | 10/23/2012 | P | PASS |
Troy Cobbley
|
|
|
ok to cover at the previously marked corrections
|
INSP-Sprinkler Rough-in | 10/18/2012 | 10/19/2012 | 10/19/2012 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for new locations where sprinkler piping can be covered. I also noted that a new wall located in the dressing room is now blocking a pendant head. It appears one pendant will need to be added and the pendant relocated to be more than 4" from the new wall. Also noted one pendant will be overspaced from the north side of the new entry vestibule when installed. Don and I agreed to add one pendant at this location.
|
INSP-Sprinkler Rough-in | 10/10/2012 | 10/10/2012 | 10/10/2012 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for additional areas where the sprinkler piping can be covered.
|
INSP-Sprinkler Rough-in | 10/9/2012 | 10/9/2012 | 10/9/2012 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for additional areas where sprinkler piping can be covered. Also see areas marked in blue that require corrections including the addtion of a sprinkler pendant in the window display.
|
INSP-Sprinkler Rough-in | 10/1/2012 | 10/1/2012 | 10/1/2012 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the location where sprinkler piping can be covered which has been clouded in red and given todays date. Also see adjacent location where three corrections will be required prior to a cover approval being given.
|
INSP-Sprinkler Rough-in | 9/25/2012 | 9/25/2012 | 9/25/2012 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the location where the sprinkler piping can be covered. It has been clouded and dated in red.
|