INSP-Final Inspection | 4/29/2013 | 4/30/2013 | 4/30/2013 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in | 4/29/2013 | 4/30/2013 | 4/30/2013 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test and forward flush passed
|
INSP-Conference | 4/25/2013 | 4/25/2013 | 4/25/2013 | P | PASS |
Troy Cobbley
|
|
|
The modified 4" pipe routing below the mezzanine is passed.
|
INSP-Sprinkler Rough-in | 4/19/2013 | 4/19/2013 | 4/19/2013 | P | PASS |
Troy Cobbley
|
|
|
Sprinkler rough-in passed. Baffles are needed between many of the sprinkler heads below the mezzanine since a min. 8'-0" is needed between the heads. Jeff and I discussed options.
|
INSP-Sprinkler Rough-in | 4/11/2013 | 4/12/2013 | 4/12/2013 | A | PASS |
Troy Cobbley
|
|
|
Sprinkler piping above hardlids is ok to cover
|
INSP-Sprinkler Rough-in | 4/11/2013 | 4/11/2013 | 4/11/2013 | P | CANC |
Troy Cobbley
|
|
|
Overbooked. Troy is going to reschedule
|