INSP-Final Inspection | 4/25/2013 | 4/26/2013 | 4/26/2013 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 4/24/2013 | 4/25/2013 | 4/25/2013 | P | CANC |
Troy Cobbley
|
|
|
Per Mike I rescheduled for tomorrow when I do the life safety inspection.
|
INSP-Sprinkler Rough-in | 4/23/2013 | 4/24/2013 | 4/24/2013 | A | PASS |
Troy Cobbley
|
|
|
Can final when the canopies are installed.
|
INSP-Sprinkler Rough-in | 4/23/2013 | 4/23/2013 | 4/23/2013 | P | CANC |
Troy Cobbley
|
|
|
per javier the as-builts are not ready. Re-scheduled for tomorrow morning.
|
INSP-Sprinkler Rough-in | 4/22/2013 | 4/22/2013 | 4/22/2013 | P | CANC |
Troy Cobbley
|
|
|
Overbooked. Javier is going to reschedule for tomorrow.
|
INSP-Sprinkler Rough-in | 3/27/2013 | 3/28/2013 | 3/28/2013 | A | PASS |
Troy Cobbley
|
|
|
Hard lids are ok to cover. I noted that there is a large shadow area with no sprinkler protection in the existing corridor that will need to be addressed prior to a final sign off.
|