INSP-Final Inspection | 6/6/2013 | 6/7/2013 | 6/7/2013 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. I had the contractor change the horn strobe in the first floor restroom to a strobe only to solve a sync problem.
|
INSP-Final Inspection | 6/5/2013 | 6/6/2013 | 6/6/2013 | A | FAIL |
Troy Cobbley
|
|
|
Need all of the notification circuits tested and updated as-builts provided prior to a final sign off.
|
INSP-Final Inspection | 6/4/2013 | 6/5/2013 | 6/5/2013 | A | FAIL |
Troy Cobbley
|
|
|
Testing continued today on the induct detectors on the first floor that control the hvac system and fire smoke dampers. See the city approved plans for devices marked "ok" in red.
|
INSP-Alarm Testing | 5/31/2013 | 6/3/2013 | 6/3/2013 | A | DONE |
Troy Cobbley
|
|
|
Finished the fire/smoke dampers on the second floor. Also performed walk through of the first floor to address any potential problems. It appears plan modifications will be needed due to additional initiating devices, additional notification devices, relocated initiating devices and NAC panels.
|
INSP-Alarm Testing | 5/30/2013 | 5/31/2013 | 5/31/2013 | A | DONE |
Troy Cobbley
|
|
|
Todays inspection was for the second floor. We verified spacing on all audio/visuals. Found several tht needed adjustment. Also five horns need to be changed to horn/strobes due to ceiling obstructions. Testing of the duct smoke detectors for hvac shutdown passed. It appears the fire/smoke dampers are wired backwards and access may be limited on some which will need to be addressed prior to the next inspection.
|
INSP-Alarm Testing | 5/30/2013 | 5/30/2013 | 5/30/2013 | A | FAIL |
Troy Cobbley
|
|
|
No approved plans on site. We all agreed to reschedule for tomorrow morning.
|