INSP-Final Inspection | 8/22/2013 | 8/22/2013 | 8/22/2013 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Alarm Testing | 8/20/2013 | 8/21/2013 | 8/21/2013 | A | DONE |
Troy Cobbley
|
|
|
Provide map at the facp and NFPA 72 forms
|
INSP-Final Inspection | 8/20/2013 | 8/21/2013 | 8/21/2013 | A | FAIL |
Troy Cobbley
|
|
|
Provide map at the facp and NFPA 72 forms.
|
INSP-Alarm Testing | 8/14/2013 | 8/20/2013 | 8/20/2013 | A | CANC |
Troy Cobbley
|
|
|
As early as possible Phone #: 2089411846 >> Inspection requested via mobile web by Brian A Inspection cancelled via mobile web on Tuesday, August 20, 2013.
|
INSP-Alarm Testing | 8/14/2013 | 8/19/2013 | 8/19/2013 | A | CANC |
Troy Cobbley
|
|
|
To be rescheduled per Brian for thursday.
|
INSP-Alarm Testing | 8/14/2013 | 8/16/2013 | 8/16/2013 | A | DONE |
Troy Cobbley
|
|
|
Items needing correction for a final sign off on this permit are to increase the candella of select corridor strobes to provide coverage at the second floor stairwells and provide coverage as dicussed at the double doors where strobe coverage exceeds 15'. Also need to set off horn/strobes to verify functionality and sync.
|
INSP-Alarm Testing | 7/17/2013 | 7/19/2013 | 7/19/2013 | A | DONE |
Troy Cobbley
|
|
|
Completed the Gym Area which included corridors and dressing rooms. Corrections have been made as noted on the previous correction notice. However it appears notification is missing from a small restroom as noted on the plans.
|
INSP-Alarm Testing | 7/17/2013 | 7/18/2013 | 7/18/2013 | A | DONE |
Troy Cobbley
|
|
|
To days inspection was for the gym area. See the city approved plans for detectors marked "ok" that have been tested. I noted two smoke detectors that will need to be added on the mezzanine level. Also one strobe on the gym floor level that is overspaced from a wall.
|