INSP-Final Inspection | 10/9/2013 | 10/10/2013 | 10/10/2013 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit work passed final walkthrough.
|
INSP-Sprinkler Rough-in | 8/19/2013 | 8/20/2013 | 8/20/2013 | A | PART |
Forrest France
|
|
|
Remainder of rough-in work completed at the deli and bakery freezer areas.
|
INSP-Sprinkler Rough-in | 7/19/2013 | 7/19/2013 | 7/19/2013 | P | PASS |
Troy Cobbley
|
|
|
OK to cover bakery freezer. The two dry pendants have been added behind the condensors.
|
INSP-Sprinkler Rough-in | 7/17/2013 | 7/18/2013 | 7/18/2013 | A | PASS |
Troy Cobbley
|
|
|
The hard lid/lay-in ceiling immediatley outside of the Bakery Freezer is ok to cover piping
|
INSP-Sprinkler Rough-in | 7/9/2013 | 7/9/2013 | 7/9/2013 | P | PART |
Forrest France
|
|
|
Inspection for coverage at the new floral cooler completed- need to seal gap at DP through cooler panel, replace with matched response type the sprinkler adjacent east of the new wall as discussed.
|
INSP-Sprinkler Rough-in | 6/28/2013 | 6/28/2013 | 7/5/2013 | P | DONE |
Troy Cobbley
|
|
|
Ok to cover 1 cooler-Don Phone #: ###-####
|