INSP-Final Inspection | 11/18/2013 | 11/18/2013 | 11/18/2013 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit work okayed for final.
|
INSP-Final Inspection | 11/14/2013 | 11/15/2013 | 11/15/2013 | A | PART |
Forrest France
|
|
|
Fire sprinkler work at the new warehouse area passed overhead inspection. Discussed light fixture locations with respect to sprinkler head coverage with electrical contractor. Final pending lacking coverage above the hall ceiling adjacent to the secure storage room where the deck sprinklers will be obstructed.
|
INSP-Sprinkler Rough-in | 9/26/2013 | 9/27/2013 | 9/27/2013 | A | PART |
Forrest France
|
|
|
Remainder of overhead work okay for ceiling cover.
|
INSP-Sprinkler Rough-in | 8/22/2013 | 8/23/2013 | 8/23/2013 | A | PART |
Forrest France
|
|
|
Okay to cover overhead fire sprinkler work at reception 101, and restrooms 102/103.
|