INSP-Final Inspection | 5/8/2015 | 5/11/2015 | 5/11/2015 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. FDC relocated, with fire dept approval, to the north side parking lot access.
|
INSP-Final Inspection | 4/20/2015 | 4/22/2015 | 4/22/2015 | P | FAIL |
Troy Cobbley
|
|
|
Inspected tamper switch interconnection with the FACP but could not do much else do to the painter starting to paint (multiple heads have been replaced due to paint), correct orfice not installed on the inspectors test and the outside alarm bell has been installed at the riser room not at the FDC which is on the other side of the building. Also I'm going to contact the fire dept about the FDC placement due to a fence being installed between the FDC and the street.
|
INSP-Final Inspection | 4/17/2015 | 4/20/2015 | 4/20/2015 | P | CANC |
Troy Cobbley
|
|
|
Cancel per Robert
|
INSP-Final Inspection | 3/11/2015 | 3/12/2015 | 3/12/2015 | A | FAIL |
Troy Cobbley
|
|
|
I left message on contacts phone that I was on the way. Arrived at job site. No one was there and all apartments locked. Project related fire alarm permit has not been scheduled and the FACP is not powered up. No inspection was performed.
|
INSP-Sprinkler Rough-in/Hydro | 8/5/2014 | 8/5/2014 | 8/5/2014 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro tests passed. Rough-in passed. Piping can be covered.
|
INSP-Sprinkler Rough-in/Hydro | 8/4/2014 | 8/4/2014 | 8/4/2014 | P | FAIL |
Troy Cobbley
|
|
|
Overhead hydro tests failed due to visable leakage at multiple pendant heads. Also two pendant heads deflectors have been damaged.
|
INSP-Sprinkler Rough-in/Hydro | 7/31/2014 | 8/1/2014 | 8/1/2014 | P | CANC |
Troy Cobbley
|
|
|
Robert is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 7/30/2014 | 7/31/2014 | 7/31/2014 | A | CANC |
Troy Cobbley
|
|
|
Cancel per Robert due to damaged piping
|
INSP-Supply line flush | 7/29/2014 | 7/30/2014 | 7/30/2014 | A | PASS |
Troy Cobbley
|
|
|
Supply line flush passed
|
INSP-Sprinkler Rough-in/Hydro | 7/25/2014 | 7/29/2014 | 7/29/2014 | A | CANC |
Troy Cobbley
|
|
|
Cancel per Robert
|
INSP-Supply line flush | 7/25/2014 | 7/28/2014 | 7/28/2014 | A | FAIL |
Craig D. Hanson
|
|
|
System is not installed per plan. Plan Mod may be needed.
|
INSP-Sprinkler Rough-in | 7/25/2014 | 7/28/2014 | 7/28/2014 | A | PASS |
Craig D. Hanson
|
|
|
Ok to cover. flush still needs to be done.
|
INSP-Sprinkler Rough-in | 7/25/2014 | 7/25/2014 | 7/25/2014 | P | CANC |
Troy Cobbley
|
|
|
No approved plans on site so Robert is going to reschedule for monday with a flush.
|
INSP-Supply line flush | 7/25/2014 | 7/28/2014 | 7/25/2014 | A | CANC |
Troy Cobbley
|
|
|
This is an ug to cover. Robert is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 1/14/2014 | 1/15/2014 | 1/15/2014 | A | FAIL |
Troy Cobbley
|
|
|
Piping as installed is ok except for an overspaced pendant and a blocked pendant. Plans need to be resubmitted due to extensive pipe re-routing and additional fittings in the supply piping which will effect the hydraulic calculations. No tenting has been performed/installed yet. No cover of piping is allowed yet.
|
INSP-Sprinkler Rough-in/Hydro | 1/14/2014 | 1/15/2014 | 1/14/2014 | A | CANC |
Troy Cobbley
|
|
|
Please call 45 min prior to inspection. Robert is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|