INSP-Final Inspection | 12/4/2014 | 12/5/2014 | 12/5/2014 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 11/20/2014 | 11/25/2014 | 11/25/2014 | P | FAIL |
Troy Cobbley
|
|
|
Simplex is not yet monitoring the low air or the tamper switch for the new pre-action valve.
|
INSP-Sprinkler Rough-in/Hydro | 11/20/2014 | 11/24/2014 | 11/24/2014 | A | PASS |
Troy Cobbley
|
|
|
Hydro test of the pre-action system passed
|
INSP-Sprinkler Rough-in | 11/3/2014 | 11/4/2014 | 11/4/2014 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for location at the clean room where piping is ok to cover.
|
INSP-Final Inspection | 10/29/2014 | 10/30/2014 | 10/30/2014 | A | PART |
Troy Cobbley
|
|
|
Pre-op and Doctors Lounge fire sprinkler is complete
|
INSP-Sprinkler Rough-in | 10/27/2014 | 10/28/2014 | 10/28/2014 | A | PASS |
Troy Cobbley
|
|
|
24 hour air test passed
|
INSP-Sprinkler Rough-in | 10/27/2014 | 10/27/2014 | 10/27/2014 | P | PART |
Troy Cobbley
|
|
|
air test on preaction system started at 10:00am with pressure marked on guage.
|
INSP-Sprinkler Rough-in | 10/22/2014 | 10/23/2014 | 10/23/2014 | A | FAIL |
Troy Cobbley
|
|
|
24 hour air test fialed.
|
INSP-Sprinkler Rough-in | 10/16/2014 | 10/17/2014 | 10/17/2014 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for rooms marked "ok" where additional piping can be covered.
|
INSP-Sprinkler Rough-in | 10/16/2014 | 10/16/2014 | 10/16/2014 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for new location where sprinkler piping can be covered.
|
INSP-Final Inspection | 9/29/2014 | 9/30/2014 | 9/30/2014 | A | PART |
Troy Cobbley
|
|
|
Sprinkler work complete in Sterile Storage.
|
INSP-Sprinkler Rough-in/Hydro | 9/26/2014 | 9/26/2014 | 9/26/2014 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for new area where piping can be covered.
|
INSP-Sprinkler Rough-in | 9/8/2014 | 9/9/2014 | 9/9/2014 | A | PASS |
Troy Cobbley
|
|
|
Don and I discussed two lights that are obstructions to the pendant sprinkler heads
|
INSP-Final Inspection | 8/15/2014 | 8/19/2014 | 8/19/2014 | A | PART |
Troy Cobbley
|
|
|
Fire sprinkler work in the Locker Rooms/Storage/PACU areas is complete.
|
INSP-Sprinkler Rough-in | 8/12/2014 | 8/13/2014 | 8/13/2014 | A | PART |
Forrest France
|
|
|
Overhead fire sprinkler work at the mens locker, shower and restrooms C100 and C101 are approved for ceiling cover.- ref. dated annotations on stamped plan set.
|
INSP-Sprinkler Rough-in | 8/11/2014 | 8/12/2014 | 8/12/2014 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for additional rooms "ok'd" for cover. The PACU area fire sprinkler work is complete.
|
INSP-Sprinkler Rough-in | 7/30/2014 | 7/31/2014 | 7/31/2014 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for areas near Lobby where sprinkler piping is ok to cover.
|
INSP-Sprinkler Rough-in | 7/29/2014 | 7/29/2014 | 7/29/2014 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for rooms at New Lobby where piping can be covered.
|
INSP-Final Inspection | 6/23/2014 | 6/24/2014 | 6/24/2014 | A | PART |
Troy Cobbley
|
|
|
Lab, Equipment Room and Lobby sprinkler work is complete.
|
INSP-Sprinkler Rough-in | 6/23/2014 | 6/23/2014 | 6/23/2014 | P | PASS |
Troy Cobbley
|
|
|
Lab and Equipment rooms sprinklers are complete. Piping in lobby area ok to cover. See city approved plans.
|
INSP-Sprinkler Rough-in | 6/9/2014 | 6/9/2014 | 6/9/2014 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for two more areas marked "ok" where the piping is ok for cover.
|
INSP-Sprinkler Rough-in | 5/22/2014 | 5/23/2014 | 5/23/2014 | A | PART |
Forrest France
|
|
|
Overhead fire sprinkler work at the lobby C122 and coffee C120 areas as marked on approved plans okayed for cover. Note * field changes are shown on as-built drawings.
|
INSP-Sprinkler Rough-in | 4/21/2014 | 4/21/2014 | 4/21/2014 | P | PASS |
Troy Cobbley
|
|
|
Fire sprinklers complete in area 1C
|
INSP-Final Inspection | 4/15/2014 | 4/16/2014 | 4/16/2014 | P | PART |
Troy Cobbley
|
|
|
Fire sprinklers complete in the new OR area.
|
INSP-Sprinkler Rough-in | 4/9/2014 | 4/10/2014 | 4/10/2014 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations marked "ok" where piping can be covered.
|
INSP-Sprinkler Rough-in | 4/8/2014 | 4/8/2014 | 4/8/2014 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the piping above the lay-in ceilings in the Kitchen area that are ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 4/4/2014 | 4/4/2014 | 4/4/2014 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test of the OR area passed.
|
INSP-Sprinkler Rough-in | 4/3/2014 | 4/3/2014 | 4/3/2014 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for additional areas where piping can be covered.
|
INSP-Final Inspection | 3/28/2014 | 3/28/2014 | 3/28/2014 | P | PART |
Troy Cobbley
|
|
|
Sprinkler work in the new Patient Wing is complete.
|
INSP-Sprinkler Rough-in | 3/27/2014 | 3/28/2014 | 3/28/2014 | A | PASS |
Troy Cobbley
|
|
|
Piping in the Cafeteria Area are ok for cover. Piping in the west side of the new addition is ok to cover (see redlined/clouded area) for location.
|
INSP-Sprinkler Rough-in | 3/25/2014 | 3/26/2014 | 3/26/2014 | A | PASS |
Troy Cobbley
|
|
|
Piping in OR room #6 and the Cafeteria area ok to cover.
|
INSP-Sprinkler Rough-in | 3/20/2014 | 3/20/2014 | 3/20/2014 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the additional O.R. where piping is ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 3/17/2014 | 3/18/2014 | 3/18/2014 | A | PASS |
Troy Cobbley
|
|
|
Hydro test of the new patient wing passed
|
INSP-Sprinkler Rough-in | 3/13/2014 | 3/14/2014 | 3/14/2014 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the OR room where piping is ok to cover.
|
INSP-Sprinkler Rough-in | 3/12/2014 | 3/13/2014 | 3/13/2014 | A | PASS |
Troy Cobbley
|
|
|
The remaining piping in the Patient Area is ok to cover. Rough-in passed for the OR area as far as mains/branchlines/hangers/seismic restraint. Will still need rough-in once the drops are cut.
|
INSP-Sprinkler Rough-in | 2/6/2014 | 2/6/2014 | 2/6/2014 | P | PASS |
Troy Cobbley
|
|
|
See area clouded in phase 1A where rough-in passed and sprinkler piping can be covered. Don and I discussed a solution to the shower areas.
|
INSP-Sprinkler Rough-in | 1/7/2014 | 1/7/2014 | 1/7/2014 | P | PASS |
Troy Cobbley
|
|
|
Todays inspection was to verify earth quake clamp, top beam clamp and retaining strap installation prior to the spray on fire proofing. It looked good.
|