Permit Information
Permit NumberFIR13-00697
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 8800 W EMERALD ST
Project NameTREASURE VALLEY HOSPITAL ADD.
Customer Number 
ePlanReviewYes
Description
The fire sprinkler scope of work consists of adding, plugging and relocating sprinklers to accommodate new wall and ceiling configuration. In addition, a grid was added to a new small patient wing an additional small grid was added to the new operating wing.

This permit is to construct a 14,320 square foot addition onto an existing single story 30,629 square foot hospital creating a new 44,949 square foot hospital. Plans approved in conjunction with BLD13-01539 for foundation and superstructure. Scope of work: construct new interior and exterior walls, installation of new plumbing, [construction of interior non-bearing walls to create additional sleeping rooms, operating rooms, and support rooms], new lighting, new accessible doors / hardware, and interior finishes. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/4/201412/5/201412/5/2014APASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection11/20/201411/25/201411/25/2014PFAIL
DetailsTroy Cobbley
Simplex is not yet monitoring the low air or the tamper switch for the new pre-action valve.
INSP-Sprinkler Rough-in/Hydro11/20/201411/24/201411/24/2014APASS
DetailsTroy Cobbley
Hydro test of the pre-action system passed
INSP-Sprinkler Rough-in11/3/201411/4/201411/4/2014APASS
DetailsTroy Cobbley
See the city approved plans for location at the clean room where piping is ok to cover.
INSP-Final Inspection10/29/201410/30/201410/30/2014APART
DetailsTroy Cobbley
Pre-op and Doctors Lounge fire sprinkler is complete
INSP-Sprinkler Rough-in10/27/201410/28/201410/28/2014APASS
DetailsTroy Cobbley
24 hour air test passed
INSP-Sprinkler Rough-in10/27/201410/27/201410/27/2014PPART
DetailsTroy Cobbley
air test on preaction system started at 10:00am with pressure marked on guage.
INSP-Sprinkler Rough-in10/22/201410/23/201410/23/2014AFAIL
DetailsTroy Cobbley
24 hour air test fialed.
INSP-Sprinkler Rough-in10/16/201410/17/201410/17/2014APASS
DetailsTroy Cobbley
See the city approved plans for rooms marked "ok" where additional piping can be covered.
INSP-Sprinkler Rough-in10/16/201410/16/201410/16/2014APASS
DetailsTroy Cobbley
See the city approved plans for new location where sprinkler piping can be covered.
INSP-Final Inspection9/29/20149/30/20149/30/2014APART
DetailsTroy Cobbley
Sprinkler work complete in Sterile Storage.
INSP-Sprinkler Rough-in/Hydro9/26/20149/26/20149/26/2014PPASS
DetailsTroy Cobbley
See the city approved plans for new area where piping can be covered.
INSP-Sprinkler Rough-in9/8/20149/9/20149/9/2014APASS
DetailsTroy Cobbley
Don and I discussed two lights that are obstructions to the pendant sprinkler heads
INSP-Final Inspection8/15/20148/19/20148/19/2014APART
DetailsTroy Cobbley
Fire sprinkler work in the Locker Rooms/Storage/PACU areas is complete.
INSP-Sprinkler Rough-in8/12/20148/13/20148/13/2014APART
DetailsForrest France
Overhead fire sprinkler work at the mens locker, shower and restrooms C100 and C101 are approved for ceiling cover.- ref. dated annotations on stamped plan set.
INSP-Sprinkler Rough-in8/11/20148/12/20148/12/2014APASS
DetailsTroy Cobbley
See the city approved plans for additional rooms "ok'd" for cover. The PACU area fire sprinkler work is complete.
INSP-Sprinkler Rough-in7/30/20147/31/20147/31/2014APASS
DetailsTroy Cobbley
See the city approved plans for areas near Lobby where sprinkler piping is ok to cover.
INSP-Sprinkler Rough-in7/29/20147/29/20147/29/2014PPASS
DetailsTroy Cobbley
See the city approved plans for rooms at New Lobby where piping can be covered.
INSP-Final Inspection6/23/20146/24/20146/24/2014APART
DetailsTroy Cobbley
Lab, Equipment Room and Lobby sprinkler work is complete.
INSP-Sprinkler Rough-in6/23/20146/23/20146/23/2014PPASS
DetailsTroy Cobbley
Lab and Equipment rooms sprinklers are complete. Piping in lobby area ok to cover. See city approved plans.
INSP-Sprinkler Rough-in6/9/20146/9/20146/9/2014PPASS
DetailsTroy Cobbley
See the city approved plans for two more areas marked "ok" where the piping is ok for cover.
INSP-Sprinkler Rough-in5/22/20145/23/20145/23/2014APART
DetailsForrest France
Overhead fire sprinkler work at the lobby C122 and coffee C120 areas as marked on approved plans okayed for cover. Note * field changes are shown on as-built drawings.
INSP-Sprinkler Rough-in4/21/20144/21/20144/21/2014PPASS
DetailsTroy Cobbley
Fire sprinklers complete in area 1C
INSP-Final Inspection4/15/20144/16/20144/16/2014PPART
DetailsTroy Cobbley
Fire sprinklers complete in the new OR area.
INSP-Sprinkler Rough-in4/9/20144/10/20144/10/2014PPASS
DetailsTroy Cobbley
See the city approved plans for locations marked "ok" where piping can be covered.
INSP-Sprinkler Rough-in4/8/20144/8/20144/8/2014PPASS
DetailsTroy Cobbley
See the city approved plans for the piping above the lay-in ceilings in the Kitchen area that are ok to cover.
INSP-Sprinkler Rough-in/Hydro4/4/20144/4/20144/4/2014PPASS
DetailsTroy Cobbley
Overhead hydro test of the OR area passed.
INSP-Sprinkler Rough-in4/3/20144/3/20144/3/2014APASS
DetailsTroy Cobbley
See the city approved plans for additional areas where piping can be covered.
INSP-Final Inspection3/28/20143/28/20143/28/2014PPART
DetailsTroy Cobbley
Sprinkler work in the new Patient Wing is complete.
INSP-Sprinkler Rough-in3/27/20143/28/20143/28/2014APASS
DetailsTroy Cobbley
Piping in the Cafeteria Area are ok for cover. Piping in the west side of the new addition is ok to cover (see redlined/clouded area) for location.
INSP-Sprinkler Rough-in3/25/20143/26/20143/26/2014APASS
DetailsTroy Cobbley
Piping in OR room #6 and the Cafeteria area ok to cover.
INSP-Sprinkler Rough-in3/20/20143/20/20143/20/2014APASS
DetailsTroy Cobbley
See the city approved plans for the additional O.R. where piping is ok to cover.
INSP-Sprinkler Rough-in/Hydro3/17/20143/18/20143/18/2014APASS
DetailsTroy Cobbley
Hydro test of the new patient wing passed
INSP-Sprinkler Rough-in3/13/20143/14/20143/14/2014PPASS
DetailsTroy Cobbley
See the city approved plans for the OR room where piping is ok to cover.
INSP-Sprinkler Rough-in3/12/20143/13/20143/13/2014APASS
DetailsTroy Cobbley
The remaining piping in the Patient Area is ok to cover. Rough-in passed for the OR area as far as mains/branchlines/hangers/seismic restraint. Will still need rough-in once the drops are cut.
INSP-Sprinkler Rough-in2/6/20142/6/20142/6/2014PPASS
DetailsTroy Cobbley
See area clouded in phase 1A where rough-in passed and sprinkler piping can be covered. Don and I discussed a solution to the shower areas.
INSP-Sprinkler Rough-in1/7/20141/7/20141/7/2014PPASS
DetailsTroy Cobbley
Todays inspection was to verify earth quake clamp, top beam clamp and retaining strap installation prior to the spray on fire proofing. It looked good.