Information based on query as of Saturday, May 18, 2024.
Permit Information
Permit NumberFIR14-00205
StatusFinaled
Name PHOENIX FIRE PROTECTION
Site Address 1115 N GARDEN ST
Project NameRiver Valley Church
Customer Number 
ePlanReviewYes
Description
The fire sprinkler scope of work consists of providing fire protection for an existing church.
Fire sprinklers used for building area increase, story increase, and for fire area. To remodel an existing 16,442 square foot church building (14,750 square foot 1st story and 1,692 square foot 2nd story). Work is to include 5 restrooms accessible to the disabled, a 2nd story toilet room accessible to the disabled, interior nonbearing walls, interior doors, a platform within the Sanctuary, stairways and a ramp to serve the new platform, other interior ramps and stairs, exterior doors, exterior windows, a direct vent gas fireplace, and interior finishes. The existing Sanctuary mezzanine will be incorporated into the existing 2nd story. Structural work includes new openings in existing masonry walls, steel headers and jambs at those new wall openings, box headers at new openings in the exterior walls of the pre-engineered metal building portion of this structure, a new exterior steel canopy and trellis with concrete footings, and new overbuilt floors and pony walls on the 2nd story to make the entire floor surface of the 2nd story at the same elevation. Special Inspection is required for welding, epoxy anchors, and expansion anchors. The pre-engineered trusses located within the Sanctuary and intended to support theatrical lighting, projection screens, etc. and the attachment of the trusses to existing steel beams are deferred submittal items. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. If the building will be occupied during construction, precautions approved by the Fire Department to ensure safe egress shall be implemented. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection2/20/20182/23/20182/23/2018APASS
DetailsTroy Cobbley
Permit finaled

Contact Leroy Anderson ###-#### 30 Min prior to Final Insp start please
Crane Alarm''s - Peter is contact ###-#### they would like to start at 9:30AM unless you can schedule them for earlier.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in/Hydro8/24/20178/25/20178/25/2017APASS
DetailsTroy Cobbley
The underground supply hydro test passed
INSP-Sprinkler Rough-in/Hydro8/22/20178/22/20178/23/2017PCANC
DetailsTroy Cobbley
Needing an UG Hydro done. Please call Scott Powada 30mins before inspection Phone #: ###-#### Inspection requested via web by Kylee Wilson
INSP-Alarm Testing8/21/20178/22/20178/22/2017AFAIL
DetailsTroy Cobbley
I could not find a record of an undergrond hydro, missing two sprinkler canopies. in the east stairwell, need the pressure relief valve setup, need backflow certified, need head box signs and calc sticker, need three pendants removed where ceilings have not been installed. Leak is fixed.
INSP-Sprinkler Rough-in8/18/20178/21/20178/21/2017APASS
DetailsTroy Cobbley
Remaining piping can be covered. Still need the leak fixed and a walk through of the second floor and the fire alarm interconnections tested.
INSP-Sprinkler Rough-in8/17/20178/18/20178/18/2017APASS
DetailsTroy Cobbley
Finished the piping rough-in inspection today. As-builts are needed showing all of the new upright coverage in the combustible concealed space above the Foyer. An additional upright head is required near a duct and another upright raised to with-in 12" of the deck.
INSP-Sprinkler Rough-in/Hydro8/15/20178/16/20178/16/2017APASS
DetailsTroy Cobbley
Overhead hydro test passed
INSP-Sprinkler Rough-in12/16/201612/20/201612/20/2016PDONE
DetailsTroy Cobbley
Scott and I met and did a preliminary inspection. The sprinkler system is currently operational. However there have apparently been wall layout and ceiling type changes. There have been pipe routing changes. Combustible spaces have no protection. A full re-submittal is needed to give an accurate representation of the actual wall and piping layout which needs to include new hydraulic calculations.
INSP-Sprinkler Rough-in12/8/201612/13/201612/13/2016ACANC
DetailsTroy Cobbley
Cancel per Scott until the city approved plans can be aquired for the inspection.
INSP-Conference12/2/201612/2/201612/6/2016ADONE
DetailsTroy Cobbley
See the fire division manager entry under the building permit
INSP-Conference12/6/201612/6/201612/6/2016PDONE
DetailsScott Arellano
Onsite visit to check on progress and meet with owner. Construction work remains in progress. Advised owners representatives to have fire protection contractors call in for testing and inspection of completed systems for partial completion.
INSP-Supply line flush10/15/201410/15/201410/15/2014PPASS
DetailsTroy Cobbley
Underground flush passed
INSP-Sprinkler Rough-in/Hydro10/1/201410/1/201410/1/2014APASS
DetailsTroy Cobbley
The remaining underground piping can be covered.
INSP-Sprinkler Rough-in9/30/20149/30/20149/30/2014PPART
DetailsForrest France
UG fire supply line approved for cover from the point of connection at the property line to the building stem wall. *Note- ductile riser and associated thrust block are incomplete at this time. Refer to dated notes on plan.