INSP-Final Inspection | 2/20/2018 | 2/23/2018 | 2/23/2018 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
Contact Leroy Anderson ###-#### 30 Min prior to Final Insp start please Crane Alarm''s - Peter is contact ###-#### they would like to start at 9:30AM unless you can schedule them for earlier.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 8/24/2017 | 8/25/2017 | 8/25/2017 | A | PASS |
Troy Cobbley
|
|
|
The underground supply hydro test passed
|
INSP-Sprinkler Rough-in/Hydro | 8/22/2017 | 8/22/2017 | 8/23/2017 | P | CANC |
Troy Cobbley
|
|
|
Needing an UG Hydro done. Please call Scott Powada 30mins before inspection Phone #: ###-#### Inspection requested via web by Kylee Wilson
|
INSP-Alarm Testing | 8/21/2017 | 8/22/2017 | 8/22/2017 | A | FAIL |
Troy Cobbley
|
|
|
I could not find a record of an undergrond hydro, missing two sprinkler canopies. in the east stairwell, need the pressure relief valve setup, need backflow certified, need head box signs and calc sticker, need three pendants removed where ceilings have not been installed. Leak is fixed.
|
INSP-Sprinkler Rough-in | 8/18/2017 | 8/21/2017 | 8/21/2017 | A | PASS |
Troy Cobbley
|
|
|
Remaining piping can be covered. Still need the leak fixed and a walk through of the second floor and the fire alarm interconnections tested.
|
INSP-Sprinkler Rough-in | 8/17/2017 | 8/18/2017 | 8/18/2017 | A | PASS |
Troy Cobbley
|
|
|
Finished the piping rough-in inspection today. As-builts are needed showing all of the new upright coverage in the combustible concealed space above the Foyer. An additional upright head is required near a duct and another upright raised to with-in 12" of the deck.
|
INSP-Sprinkler Rough-in/Hydro | 8/15/2017 | 8/16/2017 | 8/16/2017 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed
|
INSP-Sprinkler Rough-in | 12/16/2016 | 12/20/2016 | 12/20/2016 | P | DONE |
Troy Cobbley
|
|
|
Scott and I met and did a preliminary inspection. The sprinkler system is currently operational. However there have apparently been wall layout and ceiling type changes. There have been pipe routing changes. Combustible spaces have no protection. A full re-submittal is needed to give an accurate representation of the actual wall and piping layout which needs to include new hydraulic calculations.
|
INSP-Sprinkler Rough-in | 12/8/2016 | 12/13/2016 | 12/13/2016 | A | CANC |
Troy Cobbley
|
|
|
Cancel per Scott until the city approved plans can be aquired for the inspection.
|
INSP-Conference | 12/2/2016 | 12/2/2016 | 12/6/2016 | A | DONE |
Troy Cobbley
|
|
|
See the fire division manager entry under the building permit
|
INSP-Conference | 12/6/2016 | 12/6/2016 | 12/6/2016 | P | DONE |
Scott Arellano
|
|
|
Onsite visit to check on progress and meet with owner. Construction work remains in progress. Advised owners representatives to have fire protection contractors call in for testing and inspection of completed systems for partial completion.
|
INSP-Supply line flush | 10/15/2014 | 10/15/2014 | 10/15/2014 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Sprinkler Rough-in/Hydro | 10/1/2014 | 10/1/2014 | 10/1/2014 | A | PASS |
Troy Cobbley
|
|
|
The remaining underground piping can be covered.
|
INSP-Sprinkler Rough-in | 9/30/2014 | 9/30/2014 | 9/30/2014 | P | PART |
Forrest France
|
|
|
UG fire supply line approved for cover from the point of connection at the property line to the building stem wall. *Note- ductile riser and associated thrust block are incomplete at this time. Refer to dated notes on plan.
|