INSP-Final Inspection | 8/20/2014 | 8/21/2014 | 8/21/2014 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in | 8/4/2014 | 8/4/2014 | 8/4/2014 | P | PASS |
Troy Cobbley
|
|
|
The remaining sprinkler piping is ok to cover
|
INSP-Sprinkler Rough-in | 7/31/2014 | 8/1/2014 | 8/1/2014 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for additional classrooms where the piping is approved for cover.
|
INSP-Sprinkler Rough-in | 7/30/2014 | 7/30/2014 | 7/30/2014 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for new rooms ok to cover.
|
INSP-Sprinkler Rough-in | 7/28/2014 | 7/29/2014 | 7/29/2014 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for classrooms where piping is ok to cover in the "A" wing
|
INSP-Sprinkler Rough-in | 7/15/2014 | 7/15/2014 | 7/15/2014 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations where piping is ok to cover as marked with todays date.
|
INSP-Sprinkler Rough-in | 7/9/2014 | 7/10/2014 | 7/10/2014 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for rooms marked "ok" where piping can be covered.
|
INSP-Sprinkler Rough-in | 7/2/2014 | 7/3/2014 | 7/3/2014 | A | CANC |
Troy Cobbley
|
|
|
Cancelled per Todd
|
INSP-Conference | 6/25/2014 | 6/26/2014 | 6/26/2014 | P | DONE |
Troy Cobbley
|
|
|
Met with Todd and discussed the ceiling assemblies. I will need an approved detail/plan for actual field conditions for the new ceiling assemblies. It appears that upright protection may be required
|
INSP-Conference | 6/24/2014 | 6/25/2014 | 6/25/2014 | A | DONE |
Forrest France
|
|
|
Regarding fire sprinkler coverage
|