INSP-Final Inspection | 10/20/2014 | 10/21/2014 | 10/21/2014 | A | PASS |
Forrest France
|
|
|
Completed functional testing of notification appliances, verified monitoring, riser supervision, trouble condition. Documents cabinet posted. Fire alarm permit finaled.
|
INSP-Final Inspection | 10/8/2014 | 10/9/2014 | 10/9/2014 | P | PART |
Forrest France
|
|
|
Verified plan modification, netcon rating, additions and relocations of both notification and initiation devices per notes. Final pending functional testing of a/v's, need access to riser room, post documents cabinet, coordinate audible testing with building occupants advance of inspection as discussed.
|
INSP-Conference | 9/10/2014 | 9/10/2014 | 9/10/2014 | P | DONE |
Forrest France
|
|
|
|
INSP-Final Inspection | 8/26/2014 | 8/27/2014 | 8/27/2014 | A | FAIL |
Forrest France
|
|
|
Items noted include; netcon of 7 at the time of inspection, need to provide addtional notification at some areas on the 3rd and 2nd floors, relocate MP at the 3rd floor NE exit, verify sync between EST and system sensor brand notification devices in suite 275. Provide a plan modification for resubmittal to include all field changes such as added power supplies, added SD, matrix change for deletion of elevator recall, correct zones at panel, added notification devices throughout all three floor levels, floorplan changes, etc. Approved plan set to match field install.
|