INSP-Final Inspection | 10/15/2014 | 10/15/2014 | 10/15/2014 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 10/13/2014 | 10/14/2014 | 10/14/2014 | A | CANC |
Troy Cobbley
|
|
|
Cancel per Brandon until the fire alarm is ready.
|
INSP-Sprinkler Rough-in/Hydro | 10/13/2014 | 10/14/2014 | 10/14/2014 | A | PASS |
Troy Cobbley
|
|
|
OH hydro passed
|
INSP-Sprinkler Rough-in | 10/13/2014 | 10/13/2014 | 10/13/2014 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Supply line flush | 9/30/2014 | 10/1/2014 | 10/1/2014 | P | CANC |
Troy Cobbley
|
|
|
Not ready
|
INSP-Sprinkler Rough-in | 9/18/2014 | 9/18/2014 | 9/18/2014 | P | CANC |
Troy Cobbley
|
|
|
Brandon-underground flushing Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 9/16/2014 | 9/17/2014 | 9/17/2014 | P | CANC |
Troy Cobbley
|
|
|
Underground hydro - Brandon Phone #: ###-####
|
INSP-Sprinkler Rough-in | 9/3/2014 | 9/4/2014 | 9/4/2014 | A | PASS |
Troy Cobbley
|
|
|
Tenting and piping rough-in passed. Piping can be covered.
|
INSP-Sprinkler Rough-in | 9/3/2014 | 9/3/2014 | 9/3/2014 | P | FAIL |
Troy Cobbley
|
|
|
Sprinkler piping rough-in passed. Tenting failed. No piping to be covered until the tenting has been corrected and verified.
|
INSP-Sprinkler Rough-in | 8/29/2014 | 8/29/2014 | 8/29/2014 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can not be covered until a tenting inspection has been passed.
|
INSP-Sprinkler Rough-in | 6/30/2014 | 7/1/2014 | 7/1/2014 | A | PASS |
Troy Cobbley
|
|
|
Underground supply line for Building #10 is ok to cover.
|