INSP-Final Inspection | 6/29/2015 | 6/30/2015 | 6/30/2015 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 6/29/2015 | 6/29/2015 | 6/29/2015 | P | FAIL |
Troy Cobbley
|
|
|
Need signage on risers, need time on flow switches changed, need to verify bell functions. I need to walk through and verify heads.
|
INSP-Sprinkler Rough-in | 10/15/2014 | 10/16/2014 | 10/16/2014 | A | PASS |
Troy Cobbley
|
|
|
Tenting inspection passed. Piping can be covered.
|
INSP-Sprinkler Rough-in | 10/14/2014 | 10/15/2014 | 10/15/2014 | P | PASS |
Troy Cobbley
|
|
|
Sprinkler rough-in passed. Tim is ok with the changes as per email. Piping can not be covered until a tenting inspection.
|
INSP-Sprinkler Rough-in/Hydro | 10/8/2014 | 10/9/2014 | 10/9/2014 | A | PART |
Troy Cobbley
|
|
|
Overhead hydro tests passed. Piping, as installed/rough-in passed. But routeing and fitting counts have changed and per the review notes any modifications will require resubmittals. So prior to an approval for cover being given I need plan modifications and a tenting inspection.
|
INSP-Supply line flush | 10/7/2014 | 10/8/2014 | 10/8/2014 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Sprinkler Rough-in | 8/27/2014 | 8/28/2014 | 8/28/2014 | A | PASS |
Troy Cobbley
|
|
|
The underground supply piping is ok to cover.
|
INSP-Sprinkler Rough-in | 8/27/2014 | 8/27/2014 | 8/27/2014 | P | CANC |
Troy Cobbley
|
|
|
Not ready for an inspection yet due to no piping in the trench.
|