INSP-Final Inspection | 11/18/2014 | 11/19/2014 | 11/19/2014 | A | PASS |
Troy Cobbley
|
|
|
Dry system trip passed. Permit finaled
|
INSP-Final Inspection | 11/12/2014 | 11/13/2014 | 11/14/2014 | P | PART |
Forrest France
|
|
|
Fire sprinkler permit work passed final walkthrough- escutcheon replaced, tape and paper removed at service entrance head, outside waterflow bell repaired while on site. Sprinkler monitoring verified. Final pending full trip test of the new dry system valve- not completed due to weather conditions at the time.
|
INSP-Sprinkler Rough-in/Hydro | 10/29/2014 | 10/29/2014 | 10/29/2014 | P | PASS |
Troy Cobbley
|
|
|
Overhead wet and dry systems passed hydro test.
|
INSP-Sprinkler Rough-in | 10/23/2014 | 10/24/2014 | 10/27/2014 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can be covered as marked on the approved plans. This includes doghouses.
|
INSP-Sprinkler Rough-in | 10/23/2014 | 10/24/2014 | 10/24/2014 | A | PASS |
Troy Cobbley
|
|
|
24 hour air test passed
|
INSP-Sprinkler Rough-in/Hydro | 10/23/2014 | 10/24/2014 | 10/24/2014 | A | PASS |
Troy Cobbley
|
|
|
24 hour air test on dry system passed
|
INSP-Sprinkler Rough-in | 10/22/2014 | 10/23/2014 | 10/23/2014 | A | PASS |
Troy Cobbley
|
|
|
started 24 hr air test with marked guage at 8:00am
|
INSP-Sprinkler Rough-in | 10/21/2014 | 10/21/2014 | 10/21/2014 | P | PART |
Forrest France
|
|
|
OH fire sprinkler work at the grid ceilings in the kitchen, multi-purpose, and office rooms as marked and dated on approved plans okayed for cover.
|
INSP-Supply line flush | 10/20/2014 | 10/21/2014 | 10/21/2014 | A | PART |
Forrest France
|
|
|
UG fire supply line flush completed. Inspection request intended for UG permit FIR14-00521.
|
INSP-Sprinkler Rough-in | 9/23/2014 | 9/24/2014 | 9/24/2014 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations where the sprinkler piping can be covered by the new hardlids.
|