INSP-Final Inspection | 5/5/2015 | 5/6/2015 | 5/6/2015 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 5/4/2015 | 5/4/2015 | 5/4/2015 | P | FAIL |
Troy Cobbley
|
|
|
Flow switch kept sticking and appears to need replacing.
|
INSP-Final Inspection | 4/21/2015 | 4/28/2015 | 4/28/2015 | A | FAIL |
Troy Cobbley
|
|
|
The backflow preventor installed does not match the city approved plans. Also the outside electric alarm bell has not been installed. Inspetion stopped.
|
INSP-Sprinkler Rough-in | 1/22/2015 | 1/22/2015 | 1/22/2015 | P | PASS |
Troy Cobbley
|
|
|
Tenting passed. Piping can be covered.
|
INSP-Supply line flush | 1/13/2015 | 1/13/2015 | 1/13/2015 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Sprinkler Rough-in | 1/13/2015 | 1/13/2015 | 1/13/2015 | P | FAIL |
Troy Cobbley
|
|
|
This was a tenting inspection. I have concerns in four locations where it appears that extra long pendant drops will not have protection from cold air. Two are located at the master bath and two locatated at the bedrooms at the opposite end of the house.
|
INSP-Sprinkler Rough-in/Hydro | 12/31/2014 | 1/5/2015 | 1/5/2015 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. I spoke to Cam about a possible pendant head addition in the walk-in shower and I spoke to Tyler about the need for proper clearance at the cpvc riser. Piping can not be covered until a tenting inspection has been passed.
|