INSP-Final Inspection | 1/12/2018 | 1/12/2018 | 1/12/2018 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in | 8/31/2017 | 8/31/2017 | 8/31/2017 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 11/3/2016 | 11/4/2016 | 11/4/2016 | P | FAIL |
Troy Cobbley
|
|
|
No testing performed. Two strobes are placed too low and one of these two is overspaced from a side wall. Also the provided city approved fire alarm plans have been printed off too small to be legible. Provide larger plans
|
INSP-Conference | 11/1/2016 | 11/1/2016 | 11/1/2016 | P | DONE |
Troy Cobbley
|
|
|
I spoke to Mike about getting this inspection scheduled and finaled. He is going to follow up and hopefully schedule for this week.
|
INSP-Final Inspection | 9/27/2016 | 9/27/2016 | 9/27/2016 | P | CANC |
Jim Page
|
|
|
Superintendent of project, Steve Phone #: ###-#### scheduled the inspection request, alarm contractor was not notified, alarm vendor needs to be onsite for fire alarm system inspection. This inspection request cancelled and alarm vendor will need to schedule final fire alarm inspection request.
|