Information based on query as of Wednesday, April 24, 2024.
Permit Information
Permit NumberFIR17-00603
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 2855 W LOCKHEED LN
Project NameBoise Airport ARFF
Customer Number 
ePlanReviewYes
Description
[City of Boise Air Rescue & Fire Fighting Station at Boise Airport]
The fire sprinkler scope of work consists of providing a wet and dry system for an existing building with a new addition. The systems have 6” underground, backflow preventer and header. The wet system is 6” and the dry system is 4”. The systems are designed as tree type layouts.

• The underground piping is under permit FIR17-00507

[BLD17-01549]
This permit is for the 4,344 sq. ft. unoccupied space associated with BLD17-00386. A separate building permit is required for occupancy of this space. This building is fully fir sprinklered and alarmed. Any alterations to the sprinkler system will require a separate permit and shall comply with NFPA 13 as regulated by the fire department. CDM

[BLD17-00386]
Project shall comply with the 2012 International Green Construction Code as adopted by City of Boise. This project includes the remodel and expansion of the existing Air Rescue and Fire Fighting Station at the Boise Airport. The project consists of 6000 s.f. of remodeled living and office space and 4800 s.f. of new equipment storage and work space, including a 3400 s.f. apparatus bay housing two fire-fighting vehicles. Approximately 3500 s.f. of existing vehicle bay and storage space will remain. Existing exterior finishes will be removed and replaced with new insulated metal panel siding and cmu wainscot. Project includes a partial TPO reroof of the existing building including additional roof insulation, as well as new TPO roofing for the addition. Project shall comply with the 2012 International Green Construction Code as adopted by City of Boise. This building is fully fire sprinklered and alarmed. Any alterations to the sprinkler system shall comply with NFPA 13 and 72 as regulated by the fire department. CDM

Alternative Materials and Methods:

• There are no AMM at this time.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/12/201911/13/201911/13/2019PPASS
DetailsTroy Cobbley
Permit finaled.


Todd Ketterling is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in11/1/201911/4/201911/4/2019PCANC
DetailsTroy Cobbley
Todd Ketterling is the contact. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in5/23/20195/24/20195/24/2019APASS
DetailsTroy Cobbley
The Training Room and Closet are approved for cover.

Todd Ketterling is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro4/23/20194/24/20194/24/2019APASS
DetailsTroy Cobbley
The overhead 200lb hydro for the east bay dry system witnessed with no pressure loss at the guage.

Todd Ketterling is the contact. This inspection is for an overhead hydro only. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection4/22/20194/23/20194/23/2019APART
DetailsTroy Cobbley
Sprinkler work is complete for the five pendant heads in the north corridor.

Todd Ketterling is the contact. Thank you for the hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in4/18/20194/19/20194/19/2019PPART
DetailsJim Page
Partial rough to cover ispection for overhead fire sprinkler piping complete, notated the city approved drawings with yellow highlighter areas approved to cover.

Todd Ketterling is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection2/11/20192/12/20192/12/2019PPART
DetailsTroy Cobbley
Phase three sprinkler work is complete.

Todd Ketterling is the contact. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in1/31/20192/1/20192/1/2019APASS
DetailsTroy Cobbley
See the city approved plans for location marked "ok" where sprinkler piping is ok for cover.

Todd Ketterling is your contact. Thanks for the hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in12/19/201812/20/201812/20/2018APASS
DetailsTroy Cobbley
The piping above the two south side restrooms is ok for cover.
INSP-Final Inspection10/25/201810/26/201810/26/2018APART
DetailsTroy Cobbley
Phase 2 work is complete

Todd Ketterling is the contact for this final inspection. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection10/24/201810/25/201810/25/2018PCANC
DetailsTroy Cobbley
Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection10/19/201810/24/201810/24/2018PCANC
DetailsTroy Cobbley
Todd Ketterling is the contact for this final inspection. Thank you for your help. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Final Inspection10/24/201810/26/201810/24/2018ACANC
DetailsTroy Cobbley
Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Final Inspection10/24/201810/25/201810/24/2018ACANC
DetailsTroy Cobbley
Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Final Inspection10/19/201810/22/201810/22/2018APASS
DetailsTroy Cobbley
Forward flush passed
INSP-Final Inspection10/18/201810/19/201810/19/2018ACANC
DetailsTroy Cobbley
Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection10/17/201810/18/201810/18/2018AFAIL
DetailsTroy Cobbley
The interconnection with the fire alarm panel has not been pre-tested, the FDC is not in the location shown as approved on the plans, need to perform a forward flush test now since people will be utilizing the new area that the new fire sprinkler system protects.


Todd Ketterling is the contact for this final inspection. Thank you for your help. Have a nice day. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in10/10/201810/11/201810/11/2018APASS
DetailsTroy Cobbley
24 hour air test passed.
INSP-Sprinkler Rough-in10/9/201810/10/201810/10/2018PPART
DetailsTroy Cobbley
24 hour air test started at 11:00am with 41psi on the guage.
INSP-Sprinkler Rough-in/Hydro9/4/20189/5/20189/5/2018PPASS
DetailsTroy Cobbley
See the city approved plans for locations mrked "ok" ehere piping is approved for cover. I noted a missing branchline restraint that will be checked at the next inspection. Also the dry sidewall has not been installed yet under the main exit canopy. The overhead hydro's passed with no visible loss at the guage.


Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in7/26/20187/27/20187/27/2018APASS
DetailsTroy Cobbley
See the city approved plans for locations marked "ok" in red where the piping is ok for cover.


Phone #: ###-#### Inspection requested via web by Stan Beus