Permit Information
Permit NumberFIR18-00461
StatusFinaled
Name ABSOLUTE FIRE PROTECTION
Site Address 880 W RIVER ST
Project NameAfton 2 Podium / Standpipes
Customer Number 
ePlanReviewYes
Description
[The Afton Phase II - Podium]
The fire sprinkler scope of work consists of the first floor, fire pump and standpipes only. The remainder of the project will follow at a later date. The fire pump is Peerless rated at 400 Gpm @ 70 Psi. The two standpipes are manual wet. The 6” underground is supplying a 6” backflow preventer and 6” header. The first level is primarily parking. There are four levels of apartment above the podium. In addition, there are three two level townhouses and a rooftop garden. The first floor is designed as OH2.

• The underground is under permit FIR18-00338
• The four story of dwelling units above the podium is under permit BLD17-03345

[BLD17-03344]
The fire sprinkler system (NFPA 13 below and above the podium) is used for story, height, and building area increase. The apartment building will be constructed on top of the podium under permit BLD17-03345. To construct the concrete parking garage podium portion of Phase II (West building) of the Afton development. All other drawings are for reference only. When the entire building is completed, uses are expected to include parking, storage, and perhaps office, retail sales, or assembly on the 1st story; two story residential condominiums on the 2nd story; and 1 story residential condominiums on the 2nd, 3rd, 4th, and 5th stories. Work under this permit includes concrete continuous footings, concrete spread footings, concrete matt footings, concrete foundations, 3-hr concrete shear walls and bearing walls, 3-hr concrete columns, 3-hr two-way post tensioned concrete podium, and a concrete slab on grade. The podium (i.e. floor of 2nd story) will be a 12-inch-thick post tensioned concrete slab having a 3-hr fire-resistance-rating. Penetrations for plumbing pipes, roof drains, hold downs for shear walls, etc. are required to be made without cutting any reinforcement, including post tensioned tendons. Special Inspection is required for soils, concrete including post tensioning, masonry, steel including welding, anchors post-installed in hardened concrete, fire-resistance-rated through penetration fire stops, etc. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The permit for the entire building shall not be finaled and a Certificate of Occupancy shall not be issued until the condo plat that removes the interior property line is completed. This permit does not establish a Certificate of Occupancy for any portion of this building. Fire sprinkler permits and fire alarm permits are required in conjunction with future building permits. **CJW**

Alternative Materials and Methods:

• There are no AMM at this time.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/23/20199/24/20199/24/2019APASS
DetailsJim Page
Final fire sprinkler inspection complete.

10:30 am pump guy will be ready. Phone #: ###-#### Inspection requested via web by Sam Ball
INSP-Sprinkler Rough-in9/24/20199/24/20199/24/2019ADONE
DetailsJim Page
Fire pump commissioning witnessed, pump commission complete.
INSP-Sprinkler Rough-in/Hydro7/16/20197/17/20197/17/2019ADONE
DetailsJim Page
Hydrostatic test for overhead fire sprinkler piping on level 1 and standpipe witnessed, no pressure loss observed.

Hydro on first floor and standpipe Phone #: ###-#### Inspection requested via web by Sam Ball
INSP-Sprinkler Rough-in3/8/20193/8/20193/8/2019AFAIL
DetailsJim Page
Numerous heads are blocked in parking garage due to sewer drain modifications, head coverage will need to be corrected in parking garage to be code compliant.
INSP-Sprinkler Rough-in2/12/20192/12/20192/12/2019PPART
DetailsJim Page
Blow in insulation for townhome attice spaces has been verified, attic spaces and under stair cavities have been filled with blow in, fire sprinkler pipng approved for cover. Rough to cover inspection for overhead fire sprinkler piping above hardlids in level 4 corridor complete, corridor hardlids with fire sprinkler piping above the sheetrock on level 4 approved for cover.

Town homes blow in insulation. Phone #: ###-#### Inspection requested via web by Sam Ball