Information based on query as of Thursday, March 28, 2024.
Permit NumberFIR19-00012
StatusFinaled
Name STATEFIRE DC SPECIALTIES
Site Address 465 W GOWEN RD
Project NameBSD Ops & Maint. T.I.
Customer Number 
ePlanReviewYes
Description
The School district is adding a equipment shelter which State Fire will protect by connecting to the existing dry system in the main building and grade it back so that it drains to the existing building.
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/11/20193/13/20193/13/2019PPASS
DetailsJim Page
Final fire sprinkler inspection complete.

Phone #: ###-#### Inspection requested via web by jeremiah robison
INSP-Final Inspection2/26/20192/27/20192/27/2019PFAIL
DetailsJim Page
Dry system did not meet time requirements for valve trip test.

Trip test Phone #: ###-#### Inspection requested via web by jeremiah robison
INSP-Final Inspection2/14/20192/15/20192/15/2019PFAIL
DetailsJim Page
Dry pipe valve needs to be serviced, clapper did not open with inspectors test flow.

Phone #: ###-#### Inspection requested via web by jeremiah robison
INSP-Sprinkler Rough-in/Hydro2/13/20192/14/20192/14/2019PDONE
DetailsJim Page
Hydrostatic test for newly installed overhead fire sprinkler piping witnessed, no pressure loss observed.

Phone #: ###-#### Inspection requested via web by jeremiah robison
INSP-Sprinkler Rough-in/Hydro2/11/20192/12/20192/12/2019ACANC
DetailsJim Page
Temperature did not get above 40 degrees, hydro cancelled per conversarion with point of contact, inspection request will be rescheduled to coincide with allowable weather for hydrostatic test.

Phone #: ###-#### Inspection requested via web by jeremiah robison
INSP-Final Inspection2/4/20192/5/20192/5/2019ACANC
DetailsJim Page
Still need to complete hydrostatic test for newly installed overhead sprinkler piping. (weather permitting) needs to be 40 degrees or above. This request is cancelled.

Phone #: ###-#### Inspection requested via web by Matthew Lewis
INSP-Sprinkler Rough-in/Hydro2/4/20192/5/20192/5/2019ADONE
DetailsJim Page
24 hr test complete, no pressure loss observed.

24hr air test and hydro Phone #: ###-#### Inspection requested via web by Matthew Lewis
INSP-Sprinkler Rough-in/Hydro2/4/20192/4/20192/4/2019PPART
DetailsJim Page
24 hour air test started at 1PM with 41 psi on new piping.

24hr air test Phone #: ###-#### Inspection requested via web by Matthew Lewis
INSP-Final Inspection2/1/20192/4/20192/4/2019AFAIL
DetailsTroy Cobbley
Rough-in passed for the most part. There were no small documents, will need 200lb hydro, 24 hr air, trip test....ect. prior to a final.