INSP-Final Inspection | 8/21/2019 | 8/22/2019 | 8/22/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
Nick Phone #: ###-#### (change inspection to this afternoon, 8-22, per kristin dolan)
|
INSP-Final Inspection | 8/13/2019 | 8/14/2019 | 8/14/2019 | A | PART |
Troy Cobbley
|
|
|
A temporary for this permit is being given for one week. Work that needs completed is: cover the cpvc piping in the riser rooms and in the storage closets, provide one hour riser room, provide heat in the riser room. nick Phone #: ###-####
|
INSP-Sprinkler Rough-in | 8/12/2019 | 8/12/2019 | 8/12/2019 | P | FAIL |
Jim Page
|
|
|
As stated with Clint, fire sprinkler plans are under review, plan mods on 01MAY2019 and 07AUG2019 were both failed, no inspection will be performed until plans are back in issued status and modification does not result in a failure.
kristen Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 4/29/2019 | 4/30/2019 | 4/30/2019 | A | PASS |
Troy Cobbley
|
|
|
The overhead hydro test was witnessed with no visible loss at the guage. Todd Phone #: ###-####
|
INSP-Supply line flush | 4/25/2019 | 4/26/2019 | 4/26/2019 | A | PASS |
Troy Cobbley
|
|
|
Underground flush witnessed
Nick Phone #: ###-####
|
INSP-Sprinkler Rough-in | 3/7/2019 | 3/8/2019 | 3/8/2019 | A | PART |
Troy Cobbley
|
|
|
Rough-in passed. Tenting passed. Piping can be covered. Plan mods are needed again because instead of both risers being located on the first floor closet, the first floor is in the first floor closet but the second floor riser has been relocated to the second floor closet. Also heat to the wet piping in the closets has not been addressed. We also spoke about the need for a sprinkler riser monitoring system. Nick Phone #: ###-####
|
INSP-Sprinkler Rough-in | 3/7/2019 | 3/7/2019 | 3/7/2019 | P | FAIL |
Troy Cobbley
|
|
|
Revised plans are not on site and there is no access to the two first floor aparatments or to the riser room due to construction work blocking the doors
Nick Phone #: ###-####
|
INSP-Sprinkler Rough-in | 2/22/2019 | 2/22/2019 | 2/22/2019 | P | FAIL |
Troy Cobbley
|
|
|
Could not perform inspection due to the fire sprinkler contractor not submitting plan modifications for approval yet. I did perform a conference with the builder about what could be covered and what could not. We also discussed obstructions caused by lights and the placement of smoke alarms. Call ahead 20 minute - partial // Andy Phone #: ###-####
|
INSP-Sprinkler Rough-in | 2/11/2019 | 2/12/2019 | 2/12/2019 | A | DONE |
Troy Cobbley
|
|
|
Inspection was a conference for Building D. I noted that plan modifications are needed for the pipe size changes, pipe re-routing and additional heads. Also it appears separate risers are needed for the first and second floors after discussion with the plan reviewer. contact Nic Smith for schedule. Phone #: ###-#### Inspection requested via web by Shane Lesteberg
|