INSP-Final Inspection | 2/19/2019 | 2/25/2019 | 2/25/2019 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
Nick Phone #: ###-####
|
INSP-Sprinkler Rough-in | 2/19/2019 | 2/20/2019 | 2/20/2019 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
Raul Phone #: ###-####
|
INSP-Sprinkler Rough-in | 2/12/2019 | 2/12/2019 | 2/12/2019 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in area of work complete, area of work approved for cover.
|
INSP-Final Inspection | 2/12/2019 | 2/12/2019 | 2/12/2019 | P | CANC |
Jim Page
|
|
|
Tenant space is not ready for a final inspection, this request is cancelled.
Nick Phone #: ###-####
|
INSP-Final Inspection | 2/8/2019 | 2/11/2019 | 2/11/2019 | P | FAIL |
Jim Page
|
|
|
Could not locate city approved drawings, need city approved drawings/documents to perform a correct inspection.
Dan Phone #: ###-####
|