Final | 7/24/2017 | 7/24/2017 | 7/24/2017 | P | PASS |
Chad Schwendiman
|
|
|
final inspection Phone #: ###-#### Inspection requested via web by Kim Adams
|
Final | 7/10/2017 | 7/10/2017 | 7/10/2017 | A | PART |
Ben Livingston
|
|
|
final inspection (Temp occupancy) for pods 1 and 2. Francisco Is the contact.
Thank you, Phone #: ###-#### Inspection requested via web by Kim Adams temp C.O. pod 1&2
|
Rough-in | 6/12/2017 | 6/12/2017 | 6/12/2017 | P | CANC |
Chad Schwendiman
|
|
|
rough in inspection for the live work 5. Phone #: ###-#### Inspection requested via web by Kim Adams - okay to cover ERU
|
Rough-in | 6/5/2017 | 6/5/2017 | 6/5/2017 | P | PASS |
Ben Livingston
|
|
|
Rough in for the 3rd pod 2nd and 3rd floor hard lids. Francisco is the contact. Thank you. Phone #: ###-#### Inspection requested via web by Kim Adams 3rd floorand 2nd floor pod 3 soffits
|
Rough-in | 5/24/2017 | 5/24/2017 | 5/24/2017 | P | PASS |
Ben Livingston
|
|
|
rough in inspection on pod 4 hard lids and pod 3 first floor Phone #: ###-#### Inspection requested via web by Kim Adams pod3 and 4 1st floor
|
Rough-in | 5/23/2017 | 5/23/2017 | 5/23/2017 | P | PASS |
Ben Livingston
|
|
|
rough in inspection for the pod 4 hard lids Phone #: ###-#### Inspection requested via web by Kim Adams pod 4 hard lids okay
|
Rough-in | 5/22/2017 | 5/22/2017 | 5/22/2017 | A | PASS |
Ben Livingston
|
|
|
rough in inspection for pod 3 - Contact Francisco. Please call on your way. Thank you Phone #: ###-#### Inspection requested via web by Kim Adams 2nd and 3rd floor pod 3 okay
|
Rough-in | 5/15/2017 | 5/15/2017 | 5/15/2017 | P | PASS |
Ben Livingston
|
|
|
Inspection for pod 4 first floor Phone #: ###-#### Inspection requested via web by Kim Adams
|
Rough-in | 5/12/2017 | 5/12/2017 | 5/12/2017 | P | FAIL |
Ben Livingston
|
|
|
Inspection for pod 4 first floor Phone #: ###-#### Inspection requested via web by Kim Adams dryer vent needs wall furred out, need to finish condensate rough in
|
Rough-in | 5/5/2017 | 5/5/2017 | 5/5/2017 | P | PASS |
Ben Livingston
|
|
|
Rough In for Pod 4 the 2nd ; 3rd floors. Contact Francisco ###-#### Phone #: ###-#### Inspection requested via web by Dan Flaherty
|
Rough-in | 4/19/2017 | 4/19/2017 | 4/19/2017 | A | PASS |
Ben Livingston
|
|
|
Rough in inspection for this morning, pod 2. Francisco is the contact. Phone #: ###-#### Inspection requested via web by Kim Adams pod 2 1st floor okay
|
Rough-in | 4/12/2017 | 4/12/2017 | 4/12/2017 | A | PASS |
Ben Livingston
|
|
|
rough in inspection for pod 2 second and 3rd floor drop ceilings Phone #: ###-#### Inspection requested via web by Kim Adams 2nd and 3rd floor okay
|
Rough-in | 3/24/2017 | 3/24/2017 | 3/24/2017 | P | PASS |
Ben Livingston
|
|
|
Rough in Phone #: ###-#### Inspection requested via web by Kim Adams pod 2 all floors
|
Rough-in | 3/21/2017 | 3/21/2017 | 3/21/2017 | A | FAIL |
Ben Livingston
|
|
|
pod 2 all floors grid lines 4-7 Phone #: ###-#### Inspection requested via web by Kim Adams condensate piping needs to be run, dryer vent on 2nd floor is out of the wall by plumbing pipe. 2nd and 3rd floor wall needs to be fured out for dryer vent and nailpltes
|
Rough-in | 3/15/2017 | 3/16/2017 | 3/16/2017 | A | PASS |
Ben Livingston
|
|
|
first floor soffits Phone #: ###-#### Inspection requested via web by Crystal Grant 1st floor pod 1
|
Rough-in | 3/14/2017 | 3/14/2017 | 3/14/2017 | P | PASS |
Ben Livingston
|
|
|
2nd floor soffits Phone #: ###-#### Inspection requested via web by Crystal Grant 2nd floor soffits pod1
|
Rough-in | 3/8/2017 | 3/8/2017 | 3/8/2017 | P | PART |
Ben Livingston
|
|
|
rough in inspection for today for the drop ceilings on the 3rd floor Phone #: ###-#### Inspection requested via web by Crystal Gran 3rd floor hard lids ok
|
Rough-in | 2/21/2017 | 2/21/2017 | 2/21/2017 | P | PART |
Ben Livingston
|
|
|
column line 1 thru 4 Phone #: ###-#### Inspection requested via web by Crystal Grant column 1-4 walls ok, dryer vents ok to use short 90s per mech. eng. need lable with dryer lengths for final
|
Rough-in | 2/9/2017 | 2/9/2017 | 2/9/2017 | P | PART |
Ben Livingston
|
|
|
rough in inspection of the bathrooms in pod 1 Phone #: ###-#### Inspection requested via web by Crystal Grant exhaust behind tubs ok, dryer vents need walls fured out, key note 1 calls for long radius elbows, need nail plates all floors
|