Permit Information
Permit NumberMEC18-05159
StatusFinaled
Name ADVANCED HEATING & COOLING
Site Address 5700 W GOWEN RD
Project Name 
Customer NumberAdvanced01
ePlanReviewNo
Description
Alteration: installation of gas line and 2 roof top units. The client is converting from electric to gas
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final12/5/201812/6/201812/6/2018PPASS
DetailsJack Reynolds
Call ahead to Bryan @ ###-#### - he will assist the inspector with roof access. Bryan will meet the inspector on site. Phone #: ###-#### Inspection requested via web by Angie Maguire
- final ok
Final12/5/201812/5/201812/5/2018PFAIL
DetailsJack Reynolds
Please call ahead to Bryan before going out so he can meet you out there with a ladder for access. Bryan @ ###-#### Phone #: ###-#### Inspection requested via web by Angie Maguire
- breaker size for both RTU's needs to be changed out
Pressure Test10/30/201810/30/201810/30/2018PPASS
DetailsJack Reynolds
Call ahead to Dwight @ ###-#### when you are in route. He will meet you there with a ladder for access to the gas line. Phone #: ###-#### Inspection requested via web by Angie Maguire
- 60lb gas pressure test for two new gas rtu's ok
Pressure Test10/25/201810/26/201810/26/2018PCANC
DetailsJack Reynolds
Call Dwight @ ###-#### with any questions. Will need to meet Dwight on site so he will have a ladder for roof access. Call Dwight and he will meet you there. We installed new gas line for 2 roof top units. Converting from Elec to Gas. Phone #: ###-#### >> Inspection requested via web by Angie Maguire Inspection cancelled from web by: Sabrina DeHority