Final | 10/23/2019 | 10/23/2019 | 10/23/2019 | P | PASS |
Ben Livingston
|
|
|
Jake is the contact Phone #: ###-#### Inspection requested via web by stan lillquist
|
Final | 10/9/2019 | 10/9/2019 | 10/9/2019 | A | FAIL |
Ben Livingston
|
|
|
Greg is the contact. He won''t be on site so call if there is any questions. Phone #: ###-#### Inspection requested via web by stan lillquist - plastice condensate lines not approved material, need to run 3/4" pvc when grade is achieved - - need to run 2nd condensate lines - - armaflex on the roof needs to be complete, and needs u v protection -
|
Rough-in | 10/9/2019 | 10/9/2019 | 10/9/2019 | A | PASS |
Ben Livingston
|
|
|
1st floor cover inspection, Greg is the contact. He won''t be on site so call if there is any questions. Phone #: ###-#### Inspection requested via web by stan lillquist - 1st floor above grid okay -
|
Rough-in | 9/16/2019 | 9/17/2019 | 9/17/2019 | A | PASS |
Ben Livingston
|
|
|
2nd floor cover, Greg is the contact. Phone #: ###-#### Inspection requested via web by stan lillquist - 2nd floor above grid okay -
|
Mec-Aging Inspection | 8/26/2019 | 8/26/2019 | 8/26/2019 | | CANC |
Ben Livingston
|
|
|
|
Rough-in | 4/9/2019 | 4/9/2019 | 4/9/2019 | P | PASS |
Ben Livingston
|
|
|
Greg Lawrence will be the contact ###-#### Phone #: ###-#### Inspection requested via web by Debbie Marino
|
Rough-in | 2/22/2019 | 2/25/2019 | 2/25/2019 | A | PART |
Ben Livingston
|
|
|
GREG IS YOUR CONTACT Phone #: ###-#### Inspection requested via web by Kim Adams
supply duct in attic needs r8 insulation, duct seal pass
|