Final | 9/18/2019 | 9/19/2019 | 9/19/2019 | A | PASS |
Ben Livingston
|
|
|
Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN
|
Final | 8/27/2019 | 8/28/2019 | 8/28/2019 | P | PART |
Ben Livingston
|
|
|
for TCO Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN - temp C.O.-
|
Rough-in | 8/27/2019 | 8/27/2019 | 8/27/2019 | P | CANC |
Ben Livingston
|
|
|
Would like to walk with you today. Call Rob ###-#### Phone #: ###-#### >> Inspection requested via web by GREGORY ANDERSEN Inspection cancelled from web by: GREGORY ANDERSEN
|
Rough-in | 8/26/2019 | 8/26/2019 | 8/26/2019 | P | PART |
Ben Livingston
|
|
|
Roof and 1st ; 2nd Floors A ; B Please call Justin when you are on site. Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN - 1st and second floor area a,b, okay- - need to install firesmoke dampers 2nd and 4th floor electrical room per manufactures instructions fail-
|
Rough-in | 8/22/2019 | 8/22/2019 | 8/22/2019 | P | PASS |
Ben Livingston
|
|
|
-A and B 3rd and 4th floor rooms-
|
Final | 8/22/2019 | 8/22/2019 | 8/22/2019 | P | CANC |
Ben Livingston
|
|
|
Bldgs A ; B 4th and 3rd floors only Please call Justin when you arrive ###-#### Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN - A,B, 3rd and 4th floor rooms-
|
Rough-in | 8/20/2019 | 8/21/2019 | 8/21/2019 | A | PASS |
Ben Livingston
|
|
|
c stack units Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN -units C stack 1st to 4th floor--
|
Rough-in | 8/20/2019 | 8/20/2019 | 8/20/2019 | P | FAIL |
Ben Livingston
|
|
|
C stack units for final Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN -- armaflex on top of some units need to be finished--
|
Final | 8/19/2019 | 8/20/2019 | 8/20/2019 | A | CANC |
Ben Livingston
|
|
|
D stack final please Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN -- rough-in--
|
Rough-in | 8/20/2019 | 8/20/2019 | 8/20/2019 | P | PASS |
Ben Livingston
|
|
|
D stack final please Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN -- D stack rooms final only, corridoors still need labels and angle correction on fire smoke damper--
|
Final | 8/19/2019 | 8/20/2019 | 8/19/2019 | A | CANC |
Ben Livingston
|
|
|
B Stack Final please Phone #: ###-#### >> Inspection requested via web by GREGORY ANDERSEN Inspection cancelled from web by: GREGORY ANDERSEN
|
Rough-in | 8/7/2019 | 8/8/2019 | 8/8/2019 | A | PASS |
Ben Livingston
|
|
|
Breezeways Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN
|
Rough-in | 8/7/2019 | 8/7/2019 | 8/7/2019 | P | FAIL |
Ben Livingston
|
|
|
Breezeways and 4th floor common area Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN -- 4th floor ok-- -- firesmoke damper angles still not to spec--
|
Rough-in | 8/6/2019 | 8/7/2019 | 8/7/2019 | A | FAIL |
Ben Livingston
|
|
|
!st floor breezeway''s Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN - firesmoke damper angles no to manufactures instalation instructions-
|
Rough-in | 8/6/2019 | 8/6/2019 | 8/6/2019 | P | PASS |
Ben Livingston
|
|
|
D stack range venting Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN -- d 1st to 4th range vent okay, rest of range vents ok to do on room final--
|
Rough-in | 8/1/2019 | 8/1/2019 | 8/1/2019 | P | PASS |
Ben Livingston
|
|
|
Cover inspection for 3rd floor common area please Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN -- per conversation with Rob increasing size of return to allow removal of units in ceiling--
|
Rough-in | 7/31/2019 | 7/31/2019 | 7/31/2019 | A | PASS |
Ben Livingston
|
|
|
D stack trash room Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN -- D 2nd -4th floor trash rooms--
|
Rough-in | 7/30/2019 | 7/30/2019 | 7/30/2019 | P | PASS |
Ben Livingston
|
|
|
2nd floor common area Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN
|
Rough-in | 7/30/2019 | 7/30/2019 | 7/30/2019 | A | NR |
Ben Livingston
|
|
|
2nd floor common area Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN --still working--
|
Rough-in | 7/24/2019 | 7/25/2019 | 7/25/2019 | A | PASS |
Ben Livingston
|
|
|
Dryer exhaust shaft please Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN -24x24 dryer shaft 2nd to roof duct seal-
|
Rough-in | 7/15/2019 | 7/15/2019 | 7/15/2019 | P | PASS |
Ben Livingston
|
|
|
Shaft inspection for B section please Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN -MAU shaft and fire smoke dampers okay, corridor 2nd to 4th floor area B-
|
Rough-in | 7/9/2019 | 7/9/2019 | 7/9/2019 | P | PASS |
Ben Livingston
|
|
|
Cover Inspection for corridors 2-4 C stack please Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN C corridors okay fire smoke damper angles 1st to 4th floor area C okay
|
Rough-in | 7/1/2019 | 7/1/2019 | 7/1/2019 | P | PASS |
Ben Livingston
|
|
|
Area C shaft 1-4 Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN fire smoke damper clearence 1st to 4th floor okay
|
Rough-in | 6/28/2019 | 7/1/2019 | 7/1/2019 | A | PASS |
Ben Livingston
|
|
|
1st Floor Cover and C Area Shaft please Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN --1st floor area A cover--
|
Rough-in | 6/28/2019 | 6/28/2019 | 6/28/2019 | P | CANC |
Ben Livingston
|
|
|
1st floor A cover. Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN canc. per conversation with Rob
|
Rough-in | 6/27/2019 | 6/27/2019 | 6/27/2019 | P | PASS |
Ben Livingston
|
|
|
2nd floor corridor A,C and D excluding fire dampers Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN 2nd floor corridor A,C and D, and one fire/smoke damper clearence and angle in corridor
|
Rough-in | 6/25/2019 | 6/25/2019 | 6/25/2019 | P | PASS |
Ben Livingston
|
|
|
3rd floor quarters A, C, D, and Shaft for cover please Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN 3rd floor hallway A,C,D main duct shaft okay
|
Rough-in | 6/11/2019 | 6/11/2019 | 6/11/2019 | A | PASS |
Chad Schwendiman
|
|
|
1st floor B grid Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN - 117, 119, 120 okay to cover ceilings
|
Rough-in | 6/10/2019 | 6/10/2019 | 6/10/2019 | P | PASS |
Ben Livingston
|
|
|
2nd floor A for soffit inspection please Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN 2nd floor A soffits
|
Rough-in | 6/4/2019 | 6/4/2019 | 6/4/2019 | P | PASS |
Ben Livingston
|
|
|
3rd floor area a soffits okay
|
Rough-in | 6/3/2019 | 6/4/2019 | 6/4/2019 | A | CANC |
Ben Livingston
|
|
|
VRF linesets 2nd thru 4th. cover please Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN
|
Rough-in | 5/28/2019 | 5/28/2019 | 5/29/2019 | P | PASS |
Ben Livingston
|
|
|
VRF linesets 2nd thru 4th. Bathroom next to elevator Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN VRF linesets 2nd thru 4th. 4th floor a soffits
|
Rough-in | 5/22/2019 | 5/23/2019 | 5/23/2019 | A | PASS |
Ben Livingston
|
|
|
4th floor B soffit cover inspection Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN 4th floor B soffit
|
Rough-in | 5/22/2019 | 5/22/2019 | 5/22/2019 | P | PASS |
Ben Livingston
|
|
|
3rd floor B soffits Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN 3rd floor b soffits
|
Rough-in | 5/16/2019 | 5/16/2019 | 5/16/2019 | P | PASS |
Ben Livingston
|
|
|
2nd floor area B please Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN 2nd floor area B soffits okay
|
Rough-in | 5/15/2019 | 5/15/2019 | 5/15/2019 | P | PASS |
Ben Livingston
|
|
|
Area B 1st floor mechanical shaft duct Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN Area B 1st floor mechanical shaft duct accrossed from kitchen duct seal okay
|
Rough-in | 5/8/2019 | 5/8/2019 | 5/8/2019 | P | PASS |
Ben Livingston
|
|
|
Area C 1st floor cover please Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN 1st floor C soffits 3 mini split line sets 1st to 4th floor
|
Rough-in | 5/7/2019 | 5/7/2019 | 5/7/2019 | P | PASS |
Ben Livingston
|
|
|
3rd floor C Tower for Cover please Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN 3rd floor C soffits
|
Rough-in | 5/6/2019 | 5/6/2019 | 5/6/2019 | P | PASS |
Ben Livingston
|
|
|
4th floor C Tower for cover please Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN 4th floor area C soffits
|
Rough-in | 4/28/2019 | 4/29/2019 | 4/29/2019 | P | PASS |
Ben Livingston
|
|
|
1st and 2nd floor A Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN 1st 2nd floor area A pre rock
|
Rough-in | 4/28/2019 | 4/29/2019 | 4/29/2019 | A | PASS |
Ben Livingston
|
|
|
3rd floor A Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN 3rd floor area A pre rock okay
|
Rough-in | 4/26/2019 | 4/26/2019 | 4/26/2019 | P | PASS |
Ben Livingston
|
|
|
A tower inspection please Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN 4th floor area A pre rock
|
Rough-in | 4/25/2019 | 4/25/2019 | 4/25/2019 | P | PASS |
Ben Livingston
|
|
|
Cover inspection for Area D 4th floor Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN 4th floor area D soffits ok
|
Rough-in | 4/18/2019 | 4/19/2019 | 4/19/2019 | A | PASS |
Ben Livingston
|
|
|
2nd floor Area C for soffits Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN 2nd floor area C soffits okay
|
Rough-in | 4/17/2019 | 4/17/2019 | 4/17/2019 | P | PASS |
Ben Livingston
|
|
|
4th floor area B please Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN 4th floor area B pre rock okay
|
Rough-in | 4/11/2019 | 4/12/2019 | 4/12/2019 | A | PASS |
Ben Livingston
|
|
|
3rd floor cover inspection please Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN 3rd floor area D soffit okay, 3rd floor area B prerock okay
|
Rough-in | 4/9/2019 | 4/9/2019 | 4/9/2019 | P | PASS |
Ben Livingston
|
|
|
Area B 1st ; 2nd floors please Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN 1st 2nd floor area B line sets pre rock
|
Rough-in | 4/5/2019 | 4/5/2019 | 4/5/2019 | P | PASS |
Ben Livingston
|
|
|
2nd floor Cover please Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN 4th floor area c pre rock 2 nd floor area D soffits
|
Rough-in | 3/28/2019 | 3/29/2019 | 3/29/2019 | A | PASS |
Ben Livingston
|
|
|
1st Floor Soffits please Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN Area D soffit duct okay
|
Conference | 3/22/2019 | 3/25/2019 | 3/25/2019 | A | PASS |
Ben Livingston
|
|
|
Grease Duct inspection Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN 2nd layer fire wrap okay
|
Rough-in | 3/22/2019 | 3/25/2019 | 3/25/2019 | A | PASS |
Ben Livingston
|
|
|
Area C Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN 1st to3rd floor area C line sets okay
|
Rough-in | 2/13/2019 | 2/14/2019 | 2/14/2019 | A | PASS |
Ben Livingston
|
|
|
Grease exhaust duct wrap and final light test Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN 1st layer duct wrap light test okay
|
Rough-in | 2/8/2019 | 2/11/2019 | 2/11/2019 | A | PART |
Ben Livingston
|
|
|
Light Test for ductwork Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN light test from kitchen to 4th floor pass final connections at hood and curb remain
|
Rough-in | 2/4/2019 | 2/5/2019 | 2/5/2019 | A | PART |
Ben Livingston
|
|
|
3rd floor Area D Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN 1st to 3rd floor area D pre rock rough-in
|
Rough-in | 2/4/2019 | 2/4/2019 | 2/4/2019 | P | PART |
Ben Livingston
|
|
|
4th floor Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN 4th floor area D pre rock rough-in
|
Rough-in | 1/30/2019 | 1/31/2019 | 1/31/2019 | A | PART |
Ben Livingston
|
|
|
Light Test for Grease Duct and Shaft Wall Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN 3 16x16 90s pass, shaft wall ok need to see fire smoke damper clearence when installed
|
Rough-in | 1/15/2019 | 1/16/2019 | 1/16/2019 | A | PART |
Ben Livingston
|
|
|
Light test for future grease duct Contact Rob ###-#### Phone #: ###-#### Inspection requested via web by GREGORY ANDERSEN 4 8' 16x16 grease duct pass 3 16x16 90 grease duct cannot have flanges on inside fail
|
Rough-in | 1/15/2019 | 1/15/2019 | 1/15/2019 | P | CANC |
Ben Livingston
|
|
|
Light test for future grease duct Rob is the contact ###-#### Phone #: ###-#### >> Inspection requested via web by GREGORY ANDERSEN Inspection cancelled from web by: GREGORY ANDERSEN
|