Final | 3/22/2019 | 3/25/2019 | 3/25/2019 | A | PASS |
Ben Livingston
|
|
|
Phone #: ###-#### Inspection requested via web by Bob Ferrin
|
Final | 3/21/2019 | 3/22/2019 | 3/22/2019 | A | FAIL |
Ben Livingston
|
|
|
Phone #: ###-#### Inspection requested via web by Bob Ferrin conduit to condencer needs to be water tight conduit
|
Pressure Test | 3/3/2019 | 3/4/2019 | 3/4/2019 | P | PASS |
Ben Livingston
|
|
|
Phone #: ###-#### Inspection requested via web by Bob Ferrin
|
Pressure Test | 2/27/2019 | 2/28/2019 | 2/28/2019 | A | CANC |
Ben Livingston
|
|
|
This inspection was scheduled for today 2/27, and the inspector put a disposition of NR, when in reality it was ready. 3 other guys on site said he walked in, poked his head in the bathroom for five seconds and walked out. Didn''t ask where the HVAC guy is, where the furnace is, didn''t call me, nothing. And this is the same inspector that did the rough in so he knows where everything is. It is ready for a pressure test and I expect it to get inspected >> Inspection requested via web by Bob Ferrin Inspection cancelled from web by: Bob Ferrin
|
Pressure Test | 2/27/2019 | 2/27/2019 | 2/27/2019 | P | NR |
Ben Livingston
|
|
|
Phone #: ###-#### Inspection requested via web by Bob Ferrin
|
Pressure Test | 2/26/2019 | 2/27/2019 | 2/27/2019 | A | CANC |
Ben Livingston
|
|
|
Phone #: ###-#### >> Inspection requested via web by Bob Ferrin Inspection cancelled from web by: Bob Ferrin
|
Rough-in | 2/7/2019 | 2/8/2019 | 2/8/2019 | A | PASS |
Ben Livingston
|
|
|
Phone #: ###-#### Inspection requested via web by Bob Ferrin
|