Final | 12/5/2019 | 12/6/2019 | 12/6/2019 | A | PASS |
Chad Schwendiman
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak
|
Final | 11/8/2019 | 11/8/2019 | 11/8/2019 | P | FAIL |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak - range needs to be finished - condensates needs ran down house to ground - line sets needs insulation finished
|
Rough-in | 6/14/2019 | 6/14/2019 | 6/14/2019 | P | PASS |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak - R/I ok
|
Rough-in | 6/9/2019 | 6/10/2019 | 6/10/2019 | P | NR |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak
|
Rough-in | 6/7/2019 | 6/7/2019 | 6/7/2019 | P | FAIL |
Jack Reynolds
|
|
|
- condensate lines ok - man J ok -need to see 3 panasonic fans installed for drawing conditioned air to adjoining rooms - inline fan for moving air from the second floor to the first floor - electric heat source in master bathroom
|
Rough-in | 6/7/2019 | 6/7/2019 | 6/7/2019 | P | NR |
Jack Reynolds
|
|
|
CALL ME PLZ Phone #: ###-#### Inspection requested via web by Oleg Chervak - condensate lines not ready
|
Rough-in | 6/5/2019 | 6/5/2019 | 6/5/2019 | A | FAIL |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak - need man j onsite and approved by the City of Boise - condensate lines need to be a min 3/4" and of approved materials
|