Rough-in | 8/13/2020 | 8/13/2020 | 8/13/2020 | P | PASS |
Chad Schwendiman
|
|
|
SE Corridor 7th floor. Please contact Rob prior to arrival ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator
|
Rough-in | 8/12/2020 | 8/13/2020 | 8/13/2020 | A | CANC |
Chad Schwendiman
|
|
|
SE Corridor 7th floor. Please contact Rob prior to arrival ###-#### Phone #: ###-#### >> Inspection requested via web by Commercial Coordinator Inspection cancelled from web by: Commercial Coordinator
|
Rough-in | 8/12/2020 | 8/12/2020 | 8/12/2020 | A | PASS |
Jack Reynolds
|
|
|
NW corridor, 7th floor duct inspection. Please contact Rob prior to arrival ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator - NW 7th floor corner duct seal ok for insulation
|
Rough-in | 8/7/2020 | 8/10/2020 | 8/10/2020 | A | PASS |
Chad Schwendiman
|
|
|
Elevator Lobby on the 4th ; 5th Floors. Please contact Rob prior to arrival ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator - okay to cover elevator lobby's on 4th, 5th, and 6th floor
|
Rough-in | 8/7/2020 | 8/7/2020 | 8/7/2020 | P | PART |
Chad Schwendiman
|
|
|
Elevator lobby floors 2,3 ; 4. Please contact Rob prior to arrival ###-####. Phone #: ###-#### Inspection requested via web by Commercial Coordinator - Okay to cover ceilings in the elevator lobby's on the 2nd and 3rd floors
|
Rough-in | 8/5/2020 | 8/5/2020 | 8/5/2020 | P | FAIL |
Chad Schwendiman
|
|
|
R/I, Dryer Inspection, Back of House. Please contact Rob prior to arrival ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator - Need sensor for dryer vent completed, Make up air damper not funtional, Disconnects need to be readily accesible.
|
Rough-in | 7/31/2020 | 7/31/2020 | 7/31/2020 | P | PASS |
Ben Livingston
|
|
|
7th Floor Hallway Duct Inspection. Look at dryers, back of house. Please contact Rob prior to arrival ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator - dryer exhaust duct seal okay - fresh air duct seal 7th floor okay
|
Rough-in | 7/28/2020 | 7/28/2020 | 7/28/2020 | P | PASS |
Chad Schwendiman
|
|
|
Baccus House Above Ceiling Phone #: ###-#### Inspection requested via web by Commercial Coordinator
|
Rough-in | 7/27/2020 | 7/27/2020 | 7/27/2020 | P | PASS |
Chad Schwendiman
|
|
|
2nd ; 3rd floor corridor, S/E corner insulation inspection. 1st floor guest laundry ; unisex bathroom. Please contact Rob prior to arrival ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator
|
Rough-in | 7/22/2020 | 7/22/2020 | 7/22/2020 | P | PASS |
Chad Schwendiman
|
|
|
Inspection, Board Room 1st floor, South Shaft Insulation. Please contact Rob prior to arrival ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator
|
Rough-in | 7/21/2020 | 7/21/2020 | 7/21/2020 | A | PASS |
Chad Schwendiman
|
|
|
Elevator Lobby 1st Floor, 2nd Floor S.E. Shaft. Please contact Rob prior to arrival ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator - Okay to cover 1st floor lobby ceiling, duct seal on 2nd floor S.E. shaft okay
|
Rough-in | 7/20/2020 | 7/20/2020 | 7/20/2020 | P | PART |
Chad Schwendiman
|
|
|
Lobby 1st Floor, Fitness Room, S/E Shaft 4-3 Floors, 6;7 Floor Fire Damper S/E Shaft. Please contact Rob prior to arrival ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator - 1st floor lobby not ready. fitness room sofit okay to cover, duct seal okay on S.W. sgaft 3 & 4th floors. Duct seal fire/smoke damper okay on 6th & 7th floor
|
Rough-in | 7/14/2020 | 7/14/2020 | 7/14/2020 | P | PASS |
Chad Schwendiman
|
|
|
1st Floor back of house, 1st floor 6th street lobby. Please call Rob prior to arrival ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator - Okay to cover hard lid on 6th st. side of lobby, okay to cover grid ceilings in back of house and kitchen
|
Rough-in | 7/13/2020 | 7/13/2020 | 7/13/2020 | P | PART |
Chad Schwendiman
|
|
|
R/I - 1st Floor Back of the house R/I - 1st floor 6th street lobby Inspection - S/E Shaft 6-4 Please contact Rob prior to arrival ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator - S.E. shaft duct seal okay on 4th-6th Supports okay on 7th floor. !st floor need to patch insulation in back of house, need to complete damper controllers in front lobby.
|
Rough-in | 7/7/2020 | 7/7/2020 | 7/7/2020 | P | PASS |
Chad Schwendiman
|
|
|
R/I Inspection #702. Please contact Rob prior to arrival ###-####. Phone #: ###-#### Inspection requested via web by Commercial Coordinator - room 702, and the linen room fire damper okay
|
Rough-in | 7/7/2020 | 7/7/2020 | 7/7/2020 | A | CANC |
Chad Schwendiman
|
|
|
R/I Inspection #702. Please contact Rob prior to arrival ###-####. Phone #: ###-#### Inspection requested via web by Commercial Coordinator - Rescheduled for this afternoon
|
Rough-in | 7/6/2020 | 7/6/2020 | 7/6/2020 | A | PASS |
Chad Schwendiman
|
|
|
R/I inspection for #723 ; 724 ; 6th floor shaft R/I. Please call Rob prior to arrival ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator - rooms 723 and 724 okay.
|
Rough-in | 7/2/2020 | 7/2/2020 | 7/2/2020 | A | PASS |
Chad Schwendiman
|
|
|
LATE AM INPSECTION SE SHAFT 7 to 6 ROUGH IN Phone #: ###-#### Inspection requested via web by Commercial Coordinator - 7th floor okay
|
Rough-in | 7/1/2020 | 7/1/2020 | 7/1/2020 | A | PASS |
Chad Schwendiman
|
|
|
Guest Rooms 713 and 714 TOP SE Shaft R/I Phone #: ###-#### Inspection requested via web by Commercial Coordinator
|
Rough-in | 6/30/2020 | 6/30/2020 | 6/30/2020 | A | PASS |
Chad Schwendiman
|
|
|
Inspection Guestrooms 715-722. Please contact Rob prior to arrival ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator - Rooms 715-722 okay
|
Rough-in | 6/29/2020 | 6/29/2020 | 6/29/2020 | A | PASS |
Chad Schwendiman
|
|
|
Rooms 703-714. Please contact Rob prior to arrival ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator - rooms 703-714 okay
|
Rough-in | 6/26/2020 | 6/26/2020 | 6/26/2020 | P | FAIL |
Chad Schwendiman
|
|
|
R/I inspection 7th floor guest room 703-714. Please contact Rob prior to arrival ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator - exaust sub ducts must extend a minimum of 22" vertically up into the shaft.
|
Rough-in | 6/25/2020 | 6/25/2020 | 6/25/2020 | A | PASS |
Chad Schwendiman
|
|
|
Inspection S.E. shaft fire smoke damper floors 7-2. Please contact Rob prior to arrival ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator - Expansion clearances okay for fire dampers in the south east shaft
|
Rough-in | 6/18/2020 | 6/19/2020 | 6/19/2020 | A | PASS |
Ben Livingston
|
|
|
Inspection, Rooms 613 ; 614. Please contact Rob prior to arrival ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator - 613,614 soffit okay
|
Rough-in | 6/9/2020 | 6/10/2020 | 6/10/2020 | P | PASS |
Chad Schwendiman
|
|
|
Room 513 ; 514, 5th ; 6th Floor Elev. Lobby. Please contact Rob prior to arrival ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator - fire smoke damper installation okay in the elevator lobby's on the 5th, 6th, and 7th, floors, fire smoke dampers for the ice machine area okay on 5th and 6th floor, soffits in 513, and 514 okay.
|
Rough-in | 6/9/2020 | 6/9/2020 | 6/9/2020 | P | PART |
Chad Schwendiman
|
|
|
4th ; 5th floor elevation lobby inspection. Please contact Rob prior to arrival ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator - 4th floor okay, 5th floor needs framed
|
Rough-in | 6/4/2020 | 6/4/2020 | 6/4/2020 | P | PART |
Chad Schwendiman
|
|
|
2, 3, ; 4 Main Shaft Elevator Lobby. Please contact Rob prior to arrival ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator - 2nd and 3rd floor okay 4th floor still needs framing installed around the damper
|
Rough-in | 6/3/2020 | 6/3/2020 | 6/3/2020 | A | FAIL |
Chad Schwendiman
|
|
|
2, 3, ; 4th Floor main Shaft Elev. Lobby. Please contact Rob prior to arrival ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator - Need framing around fire/smoke dampers
|
Rough-in | 6/1/2020 | 6/1/2020 | 6/1/2020 | A | PASS |
Chad Schwendiman
|
|
|
R/I Fire Smoke Rooms on Floors 2,3,4. Please reach out to Rob Campbell prior to arrival Phone #: ###-#### Inspection requested via web by Commercial Coordinator - Round fire smoke dampers in the ice machine area okay on 2, 3, and 4
|
Rough-in | 5/27/2020 | 5/27/2020 | 5/27/2020 | A | PASS |
Troy James
|
|
|
R/I Rooms Only 613-602. Sealant Inspection R/I 1st Floor Pool. Please contact Rob prior to arrival. ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator 6th floor rooms ok cover as mentioned above and ok to cover ceiling in pool room.
|
Rough-in | 5/21/2020 | 5/21/2020 | 5/21/2020 | P | PASS |
Chad Schwendiman
|
|
|
R/I Room 624-614 ; 413-414. Please Contact Rob prior to arrival - ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator
|
Rough-in | 5/15/2020 | 5/18/2020 | 5/18/2020 | A | PASS |
Chad Schwendiman
|
|
|
R/I Rooms 502 ; 503. Please contact Rob prior to arrival ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator
|
Rough-in | 5/14/2020 | 5/14/2020 | 5/14/2020 | P | PASS |
Chad Schwendiman
|
|
|
6th ; 7th N.W. Shaft Fire Smoke Dampers, 5th Floor, Rooms 513-502 R/I. Please contact Rob prior to arrival ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator
|
Rough-in | 5/11/2020 | 5/11/2020 | 5/11/2020 | A | PASS |
Chad Schwendiman
|
|
|
2nd floor N.W. shaft fire smoke dampers. Please contact Rob prior to arrival. ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator
|
Rough-in | 5/8/2020 | 5/8/2020 | 5/8/2020 | A | PASS |
Chad Schwendiman
|
|
|
5th floor guest rooms 524-514. NW shaft 5, 4, 3. Please contact Rob prior to arrival ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator
|
Rough-in | 5/7/2020 | 5/7/2020 | 5/7/2020 | A | FAIL |
Chad Schwendiman
|
|
|
R/I, Cover N.W. Shaft. 5th floor guest rooms 524-514 ; 314-313. Please contact Rob prior to arrival ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator - Need to install fire/smoke dampers per manufactures instructions, rooms 514-524 not ready. rooms 313 & 314 okay to cover the soffits.
|
Rough-in | 4/30/2020 | 5/1/2020 | 5/1/2020 | A | PART |
Chad Schwendiman
|
|
|
R/I rooms 413-402. Please contact Rob if you have any questions ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator - Okay to cover rooms 403-413. Need to fix broken duct in room 402.
|
Rough-in | 4/23/2020 | 4/24/2020 | 4/24/2020 | A | PASS |
Chad Schwendiman
|
|
|
4th floor Guest Rooms 424-414, N.W. Shaft 2-6th floor seal inspection, rooms 214 ; 213 C/I. Please contact Rob with any questions. ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator - Okay to cover rooms 213, 214, and 414-424. Okay to insulate duct in nw shaft 2-6 floors.
|
Rough-in | 4/20/2020 | 4/20/2020 | 4/20/2020 | A | PASS |
Chad Schwendiman
|
|
|
Okay to cover womens bathroom ceiling on 1st floor.
|
Rough-in | 4/16/2020 | 4/17/2020 | 4/17/2020 | A | PART |
Chad Schwendiman
|
|
|
R/I inspection for 3rd floor, front street side, apt 314-302. 7th floor shaft data room side for cover. 1st floor men and women’s restrooms only R/I for cover Please contact Rob with any questions ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator - 7th floor main shaft okay to cover on data side. #rd floor rooms 302-314 okay to cover. 1st floor mens bathroom okay to cover. Womens bathroom need to cap or run duct on open tap above ceiling.
|
Rough-in | 4/14/2020 | 4/14/2020 | 4/14/2020 | A | PASS |
Chad Schwendiman
|
|
|
4th floor insulation in main shaft okay room 202, 222, 224 okay to cover
|
Rough-in | 4/9/2020 | 4/10/2020 | 4/10/2020 | A | PART |
Chad Schwendiman
|
|
|
R/I 2nd Floor Guest Rooms Main Shaft Floors 4-7 3rd Floor Shaft - 6th St Side - Guest Rooms Corridor Duct Ceiling Inspection - 4th Floor Phone #: ###-#### Inspection requested via web by Commercial Coordinator - 2nd floor guest rooms okay to cover except for 202, 222, 224. Duct seal okay on main shaft from 4th floor to roof. Guest rooms 315-324 okay to cover Duct seal on fourth floor corridoor okay.
|
Rough-in | 3/23/2020 | 3/23/2020 | 3/23/2020 | A | PASS |
Ben Livingston
|
|
|
Inspection 2;3 rd floor duct seal corridor. Please contact Rob prior to arrival. Phone #: ###-#### Inspection requested via web by Commercial Coordinator - duct insulation on shaft next to data room 2nd, 3rd floor, 2nd and 3rd floor corridor duct seal -
|
Rough-in | 3/20/2020 | 3/20/2020 | 3/20/2020 | A | PASS |
Jack Reynolds
|
|
|
Duct Seal Inspection on floor 2,3,4. Please contact Rob prior to arrival ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator - duct seal on shaft next to data room 2nd, 3rd, 4th floor ok for insulation
|
Rough-in | 3/4/2020 | 3/4/2020 | 3/4/2020 | P | PASS |
Troy James
|
|
|
Inspection 2nd floor shaft. Please contact Rob prior to arrival. ###-#### Phone #: ###-#### Inspection requested via web by Commercial Coordinator Okay subduct shaft second level.
|
Rough-in | 3/2/2020 | 3/3/2020 | 3/3/2020 | A | PART |
Troy James
|
|
|
R/I Inspection for 2nd floor guest shaft Phone #: ###-#### Inspection requested via web by Commercial Coordinator There are 3 left to complete.
|
Rough-in | 1/13/2020 | 1/14/2020 | 1/14/2020 | A | PASS |
Troy James
|
|
|
Inspection needed for duct insulation. Please contact Rob prior to arrival at ###-####. Phone #: ###-#### Inspection requested via web by Commercial Coordinator Okay to insulate misc areas. Mostly where air handlers are being installed.
|
Rough-in | 12/20/2019 | 12/23/2019 | 12/23/2019 | A | PASS |
Troy James
|
|
|
Duct Ceiling Inspection Please call Rob Campbell at ####-#### prior to arrival. Phone #: ###-#### Inspection requested via web by Commercial Coordinator Okay to insulate ducts at pool area.
|
Rough-in | 11/15/2019 | 11/18/2019 | 11/18/2019 | A | PASS |
Chad Schwendiman
|
|
|
Inspection for duct seal. Please contact Rob at ###-#### prior to arrival on-site. Phone #: ###-#### Inspection requested via web by Commercial Coordinator - Okay to insulate low pressure duct on 1st floor
|
Rough-in | 11/14/2019 | 11/14/2019 | 11/14/2019 | A | PASS |
Troy James
|
|
|
ok to insulate high pressure duct at elevator lobby and ok to cover ceiling at mock up room 223
|
Conference | 11/13/2019 | 11/14/2019 | 11/14/2019 | A | PASS |
Troy James
|
|
|
Mock-up room and general walk conference inspection. Please contact Rob at ###-#### prior to arrival on-site. Phone #: ###-#### Inspection requested via web by Commercial Coordinator Performed walk through with contractor.
|
Rough-in | 8/13/2020 | 8/18/2020 | | A | |
Chad Schwendiman
|
|
|
Final Inspection for guestrooms on floors 2 & 3. Please contact Rob prior to arrival ###-#### Phone #: ###-#### >> Inspection requested via web by Commercial Coordinator
|
Rough-in | 8/13/2020 | 8/14/2020 | | P | |
Ben Livingston
|
|
|
R/I 7th Floor Elev. Lobby. Linen rooms on floors 2,3,4, BOH Dryer. Please contact Rob prior to arrival ###-#### Phone #: ###-#### >> Inspection requested via web by Commercial Coordinator
|